SR 07-18-2023 5K
City Council
Report
City Council Meeting: July 18, 2023
Agenda Item: 5.K
1 of 5
To: Mayor and City Council
From: Rick Valte, Public Works Director, Public Works, Architecture Services
Subject: Approval of Sixth Modification to the Construction Contract with Hathaway
Dinwiddie for the City Yards Modernization Project
Recommended Action
Staff recommends that the City Council:
1. Adopt a finding that the Microgrid and Water Resources Tenant Improvements
were analyzed as part of the City Yards Master Plan Environmental Impact
Report (EIR) and Addendum, and no further review is required pursuant to the
California Environmental Quality Act (CEQA).
2. Authorize the City Manager to negotiate and execute a sixth modification to
Design-Build Contract #10371 (CCS) using mainly grant funds in the amount of
$11,400,000 with Hathaway Dinwiddie Construction Company for design and
construction services of the Microgrid and Water Resources Tenant
Improvements as part of the City Yards Modernization – Package A Project for
the Public Works Department. This would result in a five-year amended
agreement with a new total amount not to exceed $98,673,039, with future year
funding contingent on Council budget approval.
3. Authorize the Director of Public Works to issue any necessary change orders to
complete additional work within contract authority.
Summary
The City of Santa Monica’s City Yards Modernization Project was prompted by an
increase in Santa Monica’s population and workforce, rapid advancements in
technology, and the introduction of new equipment and practices. The upgrades to City
Yards would improve the operations of key city services through advanced operating
efficiencies, site safety, and implementation of sustainability goals. As a part of the
approved City Yards Master Plan, a Microgrid and Water Resources Tenant
Improvements were envisioned to meet the immediate and future needs of the Public
5.K
Packet Pg. 420
2 of 5
Works Department. Due to the COVID-19 pandemic, there was a $39,925,845 reduction
in funding for the City Yards Modernization Project which was one of the largest
enacted by Council during the covid pandemic. Project scope reductions were enacted
until alternate funding could be identified.
As part of the AB-179 Budget Act of 2022 legislation, the State’s budget authorized a
grant earmark of $10 million from the California Arts Council for the City Yards Microgrid
project. In addition, $1.5 million in available Water and Wastewater Funds for the Water
Resources Tenant Improvements were budgeted in the Fiscal Year 2022-23 Midyear
CIP Budget. Staff recommends executing a sixth amendment to the GMP design-build
contract with Hathaway Dinwiddie Construction Company (HDCC) in the amount of
$11,400,000 including the $10 million grant and $1.4 million of the Water and
Wastewater Funds for a new total amount not to exceed $98,673,039. The remaining
$100,000 will be used as budget contingency set aside to address unforeseen or
unexpected costs during the project’s implementation.
Discussion
Located at 2500 Michigan Avenue, the 14.7 -acre Santa Monica City Yards operates
seven days a week and houses the City’s Facilities Maintenance Division, Resource
Recovery and Recycling Division, Street Services Division, Fleet Maintenance Division,
Traffic Operations Division, Water Resources Division, and the Fire Department
Training Facility.
The approved City Yards Master Plan included both a Microgrid and Water Resources
Tenant Improvements. The microgrid would include a photovoltaic array and battery
backup storage and would provide efficient, reliable, and cost-effective energy that has
a low environmental and carbon impact. It could also store energy, allowing the City
Yards and eventually the surrounding businesses to continue critical operations in case
of a major power outage. The tenant improvement project would relocate and construct
a new bulk material storage, decant area, laydown, and equipment storage at the City
Yards to support operations in the Water Resources Division. This project would
5.K
Packet Pg. 421
3 of 5
relocate the storage area away from the homes on the east side of the City Yards and
minimize noise and aesthetic impacts to the adjacent residents.
This work was originally included in Package A of the City Yards Modernization Project
but was later eliminated on May 5, 2020, as part of dramatic reductions to the Capital
Improvement Program as a result of the economic impacts of t he COVID-19 pandemic.
Among the largest reductions was the $39,925,845 decrease in funding for the City
Yards Modernization Project. Staff continued to identify alternate funding sources and
pursue opportunities to fund the completion of the eliminated scope of work envisioned
in the City Yards Master Plan.
The availability of $10 million of grant funding for the Microgrid and $1.5 million Water
and Wastewater funding for the Water Resources Tenant Improvements approved in
the Fiscal Year 2022-2023 Midyear Budget by Council on April 11, 2023 (Attachment C)
along with the capacity of the design-build team to advance this work due to the deferral
of Phase 3 of the City Yards Modernization Project, present a unique opportunity to
efficiently complete these project components now. The operational efficiencies of
developing the new Microgrid and Water Resources Tenant Improvements concurrently,
as well as the time saved through the expedited design -build delivery method, allow the
City to reduce overhead and escalation costs associated with deferring this project
scope further.
Environmental Analysis
This project has previously been analyzed through certification of the City Yards
Modernization Project EIR (State Clearinghouse No. 2017111053) that was certified on
January 16, 2019, with an Addendum approved in May 2022. This project is one
component of the City Yards Modernization Project that was described and analyzed in
the City Yards Modernization Project EIR. Therefore, no further environmental
documentation is required.
Past Council Actions
5.K
Packet Pg. 422
4 of 5
Meeting Date Description
10/25/2016
(Attachment A)
Award Design Contract for the City Yards Modernization Project
6/14/2022
(Attachment B)
Fifth Modification to GMP with HDCC
4/11/2023
(Attachment C)
Fiscal Year 2022-2023 Midyear Budget
Financial Impacts and Budget Actions
Staff seeks authority to approve available funding from the Water and Wastewater
Funds and Miscellaneous Grant Funds to increase the amount of the GMP agreement
with HDCC for design and construction services for the relocation of the bulk material
and storage facility and Microgrid included in the City Yards Modernization Project
Package A.
Agreement Modification Request
Agreement
#
Current
Authorized
Amount
FY 2022-23
Budget
Modified Request
Amount
Dept/CIP Account # Total Revised
Contract
Amount
10371 $0 $10,000,000 C2008760.689000 $10,000,000
10371 $0 $1,050,000 C5008790.689000 $1,050,000
10371 $0 $350,000 C5108790.689000 $350,000
10371 $1,750,000 $0 C5408070.689000 $1,750,000
10371 $48,426,082 $0 C0105410.689000 $48,426,082
10371 $19,148,100 $0 C0105410.689720 $19,148,100
10371 $7,406,100 $0 C5005410.689410 $7,406,100
10371 $1,084,600 $0 C5105410.689000 $1,084,600
10371 $60,300 $0 C7505410.689000 $60,300
10371 $1,500,000 $0 C7007720.689000 $1,500,000
10371 $650,000 $0 C5104870.689000 $650,000
10371 $372,857 $0 C2006830.689000 $372,857
10371 $6,350,000 $0 C0107500.689000 $6,350,000
10371 $200,000 $0 C0104580.689000 $200,000
10371 $325,000 $0 01500020.52914C $325,000
$87,273,039 $11,400,000 Total $98,673,039
Future year funding is contingent on Council budget approval.
5.K
Packet Pg. 423
5 of 5
Prepared By: Sebastian Felbeck, Senior Construction Manager
Approved
Forwarded to Council
Attachments:
A. Staff Report - Award Design Contract for the City Yards Modernization Project
(Web Link)
B. Staff Report - Fifth Modification to GMP with HDCC (Web Link)
C. Oaks Initiative Form - Hathaway Dinwiddie 2023-06-08
D. Staff Report - Fiscal Year 22-23 Midyear Budget Staff Report (Web Link)
E. Contracts
5.K
Packet Pg. 424
5.K.c
Packet Pg. 425 Attachment: Oaks Initiative Form - Hathaway Dinwiddie 2023-06-08 [Revision 1] (5759 : Mod 6 - City Yards Modernization Construction
5.K.c
Packet Pg. 426 Attachment: Oaks Initiative Form - Hathaway Dinwiddie 2023-06-08 [Revision 1] (5759 : Mod 6 - City Yards Modernization Construction
5.K.c
Packet Pg. 427 Attachment: Oaks Initiative Form - Hathaway Dinwiddie 2023-06-08 [Revision 1] (5759 : Mod 6 - City Yards Modernization Construction
5.K.e
Packet Pg. 428 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 429 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 430 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 431 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 432 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 433 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 434 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 435 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 436 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 437 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 438 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 439 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 440 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 441 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 442 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 443 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 444 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 445 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 446 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 447 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 448 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 449 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 450 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 451 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 452 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 453 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 454 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 455 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 456 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 457 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 458 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 459 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 460 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 461 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 462 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 463 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 464 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 465 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 466 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 467 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 468 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 469 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 470 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 471 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 472 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 473 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 474 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 475 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 476 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 477 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 478 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 479 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 480 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 481 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 482 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 483 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 484 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 485 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 486 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 487 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 488 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 489 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 490 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 491 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 492 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 493 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 494 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 495 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 496 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 497 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 498 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 499 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 500 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 501 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 502 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 503 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 504 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 505 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 506 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 507 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 508 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 509 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 510 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 511 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 512 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 513 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 514 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 515 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 516 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
FIRST AMENDMENT TO DESIGN/BUILD AGREEMENT NO. 10371 (CCS)
This First Amendment to Design/Build Agreement No. 10371 (CCS) (“First
Amendment”), is entered into as of _________________ (“Execution Date”), by and
between the City of Santa Monica, a municipal corporation (“City”), and Hathaway
Dinwiddie Construction Company (“Design/Builder”), and is made with reference to
the following:
RECITALS
A. On or about September 27, 2018, the City and Design/Builder entered into a
Design-Build Agreement No. 10371 (CCS) (“Agreement”) for the design and
construction of the City Yards Modernization Project.
B. The City and Design/Builder desire to enter into this First Amendment to
establish a Guaranteed Maximum Price (“GMP1”) for the Foundation Only
portion City Yards Modernization Project (“GMP1 Scope”) under the terms and
conditions set forth herein.
C. The City and Design/Builder agree that notwithstanding anything to the contrary
herein, nothing in this First Amendment shall commit the City to pay for or
entitle Design/Builder to receive any compensation for the Project other than for
GMP1 Scope until such time as the City and Design/Builder agree upon and
execute a Second Amendment to establish a Guaranteed Maximum Price
(“GMP2”) for the construction portion of the Project (“GMP2 Scope”).
D. The City and Design/Builder understand and agree that “Package A” in this First
Amendment is a collective reference to GMP1 Scope and GMP2 Scope (all
above ground work not included in GMP1).
TERMS AND CONDITIONS
NOW, THEREFORE, it is mutually agreed by and between the undersigned
parties as follows:
1. Recitals. The City and Design/Builder agree that the above Recitals are true and
correct and incorporated into the terms and conditions of this First Amendment.
2. Construction Documents. A list of Construction Documents for GMP1 Scope
is attached hereto as Exhibit A-1. All references in this First Amendment,
General Conditions, and General Requirements to the Preliminary Design
Documents shall henceforth be understood to refer to the new list of Drawings,
Specifications, and Reports attached hereto as Exhibit A-1. The City and
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
8/27/2019
5.K.e
Packet Pg. 517 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
Design/Builder agree that GMP1 Scope is limited to the Work set forth in the
plans and drawings listed in Exhibit A-1.
3. Contract Price. The Contract Price for this First Amendment shall consist of:
(i) the Preconstruction GMP amount previously authorized in the Agreement in
the amount of EIGHT MILLION, FIVE HUNDRED SIXTY-TWO
THOUSAND, EIGHT HUNDRED FIFTY-SEVEN DOLLARS ($8,562,857);
plus (ii) GMP1 authorized by this First Amendment for GMP1 Scope in the
amount of THIRTY-SIX MILLION NINE HUNDRED AND NINETY-NINE
THOUSAND, EIGHT HUNDRED EIGHTEEN DOLLARS ($36,999,818).
4. Schedule of Values. The agreed Schedule of Values for GMP1 and GMP1 Scope
shall be as set forth in Exhibit D-1.
5. Design/Builder Qualifications. The Contract Price is conditioned on and
subject to the Exceptions, Qualifications, Exclusions attached hereto in Exhibit
D-1.
6. Construction Schedule. The updated construction schedule is attached hereto as
Exhibit C-1.
7. City Representative. Section 1.9 of the Agreement (City Representative) is
hereby amended by replacing the name “Rebecca Abano” with the name
“Christopher Dishlip.”
8. Construction Contingency. Section 2.4.1 of the Agreement (Design/Builder
Contingency) is hereby amended by deleting and replacing the first sentence of
the text in Section 2.4.1 with the following sentence:
The Construction GMP shall include a 5% contingency
(Design/Builder Contingency)
Section 2.4.3 of Agreement (City Contingency) is hereby amended by deleting
and replacing the first sentence of the text in Section 2.4.3 with the following
sentence:
The Construction GMP shall include a 0% contingency (City
Contingency)
9. Contract Time. Section 3.3.2 of the Agreement (Construction Phase) is hereby
amended by deleting and replacing all of the text in Section 3.3.2 with the
following sentence:
Design/Builder shall achieve Substantial Completion of the Work
for Package A within One Thousand Two Hundred Fifty (1,250)
Days after City’s issuance of a Construction Notice to Proceed.
Notwithstanding anything to the contrary herein, this provision
shall only take effect in the event that the City and Design/Builder
execute a Second Amendment for GMP2 and GMP2 Scope.
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
5.K.e
Packet Pg. 518 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
10. Compensable Delay. Section 3.5.2.1 of the Agreement (Damages to Contractor)
is hereby amended by deleting and replacing the first sentence of the text in
Section 3.5.2.1 with the following sentence:
Subject to Section 3.5.1 and provided that the City and
Design/Builder execute a Second Amendment for GMP2 and
GMP2 Scope, the Contract Price shall be increased by the fixed
amount of TWENTY-ONE THOUSAND, TWO HUNDRED
THIRTEEN DOLLARS ($21,213) ("Compensable Delay Rate")
for each Day of extension to the Contract Time for Substantial
Completion of the Work that Design/Builder is entitled to be
granted under the terms of this Agreement and the General
Conditions due to Compensable Delay occurring after execution of
this Agreement and prior to Substantial Completion and affecting
Substantial Completion of the Work, but only to the extent that the
Compensable Delay is not concurrent with (1) an Inexcusable
Delay or (2) another Excusable Delay that is not also a
Compensable Delay.
11. Liquidated Damages to the City. Section 3.6 of the Agreement (Liquidated
Damages to the City) is hereby amended by deleting and replacing all of the text
in Section 3.6 with the following paragraph:
IF DESIGN/BUILDER FAILS TO ACHIEVE SUBSTANTIAL
COMPLETION OF THE WORK WITHIN THE CONTRACT
TIME REFERRED TO IN PARAGRAPH 3.3.2 OF THIS
AGREEMENT (AS ADJUSTED BY CHANGE ORDER FOR
EXTENSIONS PERMITTED BY THE CONTRACT
DOCUMENTS), CITY WILL INCUR DAMAGES, THE
AMOUNT OF WHICH WILL BE DIFFICULT OR IMPOSSIBLE
TO ESTABLISH WITH CERTAINTY, INCLUDING BUT NOT
LIMITED TO INEFFICIENCY AND DISRUPTION OF CITY'S
OPERATIONS. THE PARTIES THEREFORE AGREE THAT
FOR EACH DAY PAST THE SUBSTANTIAL COMPLETION
DATE REFERRED TO IN PARAGRAPH 3.3.2 (AS ADJUSTED
BY CHANGE ORDER FOR THE EXTENSIONS PERMITTED
BY THE CONTRACT DOCUMENTS) THAT THE WORK IS
NOT SUBSTANTIALLY COMPLETE, DESIGN/BUILDER
SHALL PAY CITY THE SUM OF FIVE THOUSAND, SEVEN
HUNDRED SEVENTY-FOUR DOLLARS ($5,774) PER DAY
AS LIQUIDATED DAMAGES. THIS SUM REPRESENTS A
REASONABLE EFFORT TO ESTIMATE FAIR
COMPENSATION FOR THE FORESEEABLE LOSSES CITY
WILL INCUR ON ACCOUNT OF DELAYS IN SUBSTANTIAL
COMPLETION OF THE WORK AND IS NOT A PENALTY.
NOTWITHSTANDING ANYTHING TO THE CONTRARY
HEREIN, THIS PROVISION SHALL ONLY TAKE EFFECT IN
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
5.K.e
Packet Pg. 519 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
THE EVENT THAT THE CITY AND DESIGN/BUILDER
EXECUTE A SECOND AMENDMENT FOR GMP2 AND GMP2
SCOPE.
12. Self-Performed Work. Section 4.5.5 of the Agreement (Self-Performed Work)
is hereby amended by deleting and replacing all of the text in Section 4.5.5 with
the
following paragraph:
No portions of the Work shall be self-performed or proposed to be
self-performed by Design/Builder without prior Approval by City,
which may be granted or withheld in City’s sole discretion.
Requests for Approval by City of self-performed Work shall be
accompanied by documentation demonstrating (i) that
Design/Builder has the capability and experience to self-perform
the scope of Work proposed to be self-performed by
Design/Builder and (ii) the cost savings to the Project, as
evidenced by, without limitation, competitive prices from at least
three (3) trade subcontractors for the scope of Work proposed to
be self-performed by Design/Builder and (iii) a proposed lump
sum price for Work to be self-performed by Design/Builder.
Submission of a lump sum proposal to self-perform Work
constitutes a representation and binding commitment by
Design/Builder that if requested by City it will perform such
Work for the lump sum price proposed. Provided that the City, in
its sole discretion, approves the amount as competitive, the
Design/Builder may self-perform the cast-in-place concrete
portion of the Work for a fixed, lump sum price of Four Million,
Four Hundred Nineteen Thousand, Eight Hundred Fourteen
Dollars ($4,419,814); provided, however, that in consideration of
the City’s so agreeing, the Design/Builder agrees that
notwithstanding anything else stated in the Contract Documents to
the contrary, Design/Builder guarantees that the Costs of Work to
complete said portion of the Work shall not exceed the agreed
lump sum price set forth herein and that any Costs of Work
incurred in excess thereof in performance of the cast-in-place
concrete portion of the Work, whether incurred by Design/Builder
or others, shall be borne by Design/Builder at its own expense,
not as a Cost of Work and shall not be reimbursed in any form by
City, including, without limitation, from Contingency. Said
guaranteed lump sum price for the cast-in-place concrete portion
of the Work shall only be adjusted for deletions or Scope Changes
to the concrete portion of the Work authorized by Change Order.
13. Labor Costs. Section 6.1.2 of the Agreement is hereby amended by deleting and
replacing the last sentence of the text in Section 6.1.2 with the following
sentence:
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
5.K.e
Packet Pg. 520 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
The cost of those services is estimated to be SIX MILLION, NINE
HUNDRED NINETY-TWO THOUSAND, THREE HUNDRED
THIRTY-SIX DOLLARS ($6,992,336), through the construction
phase of City Yards Modernization Project. This amount is
included within the General Conditions line item of the Schedule
of Values in Exhibit D-1 and includes the time for the key
personnel listed in Exhibit B-1 at the updated wage rates spelled
out in Exhibit E-1.
Section 6.1.3 of the Agreement is hereby amended by deleting and replacing the
first sentence of the text in Section 6.1.3 with the following sentence:
Design/Builder acknowledges and agrees that the amount
authorized for General Conditions in Section 6.1.2 includes taxes,
insurance, contributions, assessments and benefits required by law
or collective bargaining agreements, and, for personnel not covered
by such agreements, customary benefits such as sick leave and
medical and health benefits and shall all be included as part of the
fully-burdened updated wage rates spelled out in Exhibit E-1. No
additional compensation for these staff members shall be
considered.
14. Design/Builder Fee. Section 9.0 of the Agreement (Design/Builder Fee) is
hereby amended by deleting and replacing all text in Section 9.0 with the text
below:
The Contract Price includes the Design/Builder's Fee. The
Design/Builder's Fee (detailed in Exhibit D-1) for the performance
of Work includes the following mark-ups for the Construction Phase
of the City Yards Modernization Project:
ITEM MARK-UP
All insurance 1.00%
All permit fees 2.95%
Cost(s) of Work performed by the
Design Professionals after GMP
Amendments, reimbursable by
City
2.95%
Cost(s) of Work performed by the
Trade Contractors after GMP
Amendments, excluding all
permit fees reimbursable by City.
2.95%
15. Bonds. Section 12.3.1 of the Agreement is hereby amended by deleting and
replacing the first sentence of the text in Section 12.3.1 with the following
sentence:
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
5.K.e
Packet Pg. 521 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
Prior to commencing any construction of the Work,
Design/Builder shall file with City a good and sufficient labor and
material payment bond (Payment Bond) and performance bond
(Performance Bond) in the amount of no less than THIRTY-SIX
MILLION NINE HUNDRED AND NINETY-NINE
THOUSAND, EIGHT HUNDRED EIGHTEEN DOLLARS
($36,999,818).
16. Notices. Section 16.2 of the Agreement (Addresses) is hereby amended by
replacing the name “Rebecca Abano” with the name “Christopher Dishlip.”
17. Familiarity with Project Site Conditions. Section 5.1 of the General
Conditions is hereby deleted.
18. Differing Site Conditions. Section 7.6.2 of the General Conditions is hereby
amended by deleting and replacing the first sentence of the text in Section 7.6.2
with the following sentence:
Differing Site Conditions are those conditions, located at the Site or in
Existing Improvements encountered by Design/Builder that constitute:
19. List of Exhibits. The following list of Exhibits are attached to this First GMP
Amendment and incorporated herein and into the Agreement by this reference:
Exhibit 1: Oaks Initiative Disclosure Form dated 04/16/2019
Exhibit 2: Living Wage Ordinance Certification – Not Applicable
Exhibit 3: Insurance dated 07/19/2019
Exhibit 4: Performance Bond dated 07/12/2019
Exhibit 5: Prevailing Wage Job Notice and Acknowledgement Forms
Exhibit A-1: Construction Documents dated 05/16/2019
Exhibit B-1: Key Personnel – Construction dated 07/01/2019
Exhibit C-1: Updated Project Schedule dated 05/13/2019 &
Logistics/Construction Mitigation Impact Plan dated 06/12/2019
Exhibit D-1: Schedule of Values, Qualifications and Exceptions through
Construction of underground/foundation work on the City Yards
Modernization – Package A dated 06/03/2019
Exhibit E-1: Updated Wage Rates dated 07/01/2019
Exhibit F-1: Sub-contractor Agreement form dated 07/01/2019
///
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
5.K.e
Packet Pg. 522 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
20. Agreement in Full Force and Effect. Except as expressly modified by this First
Amendment, all other terms and conditions of the Agreement shall be and remain
in full force and effect.
In witness whereof, the City and Design/Builder have executed this First
Amendment as of the date and year first written above.
ATTEST:
______________________________
DENISE ANDERSON-WARREN
City Clerk
APPROVED AS TO FORM:
______________________________
LANE DILG
City Attorney
CITY OF SANTA MONICA,
a municipal corporation
By: ____________________________
RICK COLE
City Manager
ABC Corporation
#VENDOR
By: ____________________________
DocuSign Envelope ID: 2ED05FCC-BD76-40B0-B5C1-FE39F4E1668A
8/26/2019
Lane Dilg
City Attorney
Hathaway Dinwiddie Construction Company
Sr. Vice President
Rashmi Mehta
8/26/2019
City Manager
Rick Cole
8/27/2019
Denise Anderson-Warren
City Clerk
8/28/2019
5.K.e
Packet Pg. 523 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
RequestDate:
ContractInformation
10371 (CCS)
HathawayDinwiddieConstructionDinwiddieConstru
CityYardsModernizationͲPackageA SP2396
PROPOSEDCHANGES:SeeExhibitAfordetails.
Contractor:Contractor'sVendor#360339
Project: Project#
ProjectManager:SebastianFelbeck Division:ArchitectureServices
CityofSantaMonica 4/21/20
CHANGEORDER
Contract# ChangeOrder(CO)# CouncilApprovalDate:12/10/19
CHANGEORDERAMOUNT $
I. CONTRACTSUMMARY
A. Originalcontractamount: $
B. PreviousChangeOrders $
C. ThisChangeOrder $
D. Newcontractamount $
II. OFFSITEWORKSUMMARY
(Totalcumulativedollaramountofalloffsiteworkmaynotexceed$100,000)
A. AmountofthisCOthatisforoffsitework: $
B. TotalcumulativeamountofalloffsiteworkafterthisCO: $
III. SCHEDULESUMMARY
A. Originalcontractstartdate
B. Originalcompletiondate
C. Durationoforiginalcontract(calendardays)
D. Previouslyadjustedcompletiondate
E. NumberofdaysthecontractwillbeextendedbythisCO:
F. ThedateofSubstantialCompletionasofthisCO:
IV. ACCOUNTALLOCATIONS
AccountNumber: $
AccountNumber: C0105410.689000 $
AccountNumber: $
AccountNumber: $
AccountNumber: $
AccountNumber: $
AccountNumber: $
AmountofthisChangeOrder: $
0.00
28,100,182.00
73,662,857.00
45,562,675.00
28,100,182.00
C7007720.689000 1,500,000.00
C5104870.689000 650,000.00
C7505410.689000 60,300.00
C5105410.689000 1,084,600.00
C0105410.689720 16,148,100.00
C5005410.689000 7,406,100.00
12/2/2022
1,251,082.00
28,100,182.00
0.00
0.00
7/1/2019
12/2/2022
1250
12/2/2022
0
Page1ofϰ
*/%#))0!'*+!
5.K.e
Packet Pg. 524 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
RequestDate:
ContractInformation
10371 (CCS)
HathawayDinwiddieConstructionDinwiddieConstru
CityYardsModernizationͲPackageA SP2396
PROPOSEDCHANGES:SeeExhibitAfordetails.
Contractor:Contractor'sVendor#360339
Project: Project#
ProjectManager:SebastianFelbeck Division:ArchitectureServices
CityofSantaMonica 4/21/20
CHANGEORDER
Contract# ChangeOrder(CO)# CouncilApprovalDate:12/10/19
V. APPROVALS
Date Date
Date Date
Date
OPTIONALͲClientDepartmentRepresentative
FUNDSAVAILABILITYCERTIFICATION:
Date
#DIVISIONHEAD #PWDIRECTOR
#CLIENTDEPARTMENT
#FINANCE
The signing of a Change Order indicates that the parties have reached a full resolution, settlement and
accord, and satisfaction with respect to all claims for cost and extensions of time that were asserted,
or that could have been asserted, whether known or unknown at the time of execution of the Change
Order, and that are related to the subject matter of the Change Order, including without limitation all
claims, costs or damages for delay, disruption, hindrance, interference, extended or extraordinary
direct and indirect overhead, multiplicity of Changes, loss of productivity labor or material cost
escalations, inefficiency, the "impact" of the Change on the Work, legal expenses, consultant costs,
interest, lost profits or revenue, bond or insurance costs, currency fluctuations, changes in taxes or
otherrelatedclaims,costsordamages,andallCompensableDelaycostsassociatedwiththischange.
#PM #CONTRACTOR
Page2ofϰ
*/%#))0!'*+!
!-.%)!'!&
,*)-.,/.%*))#!,,%!,!-% !).
-$(%!$.
+%.',*#,()#!,
$,%-.*+$!,%-$'%+/-)'%)!
%,!.*,*"/'%*,&-
*).,.-**, %).*,
*$),,1
5.K.e
Packet Pg. 525 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
Request Date:
Contract Information
10371 (CCS)2
Hathaway Dinwiddie Construction
City Yards Modernization - Package A SP2396
PROPOSED CHANGES: See Exhibit A for details.
Project Manager:Sebastian Felbeck Division:Architecture Services
City of Santa Monica 9/2/21
CHANGE ORDER
Contract # Change Order (CO) # Council Approval Date:4/27/21
Contractor: Contractor's Vendor #360339
Project: Project #
CHANGE ORDER AMOUNT $
I. CONTRACT SUMMARY
A. Original contract amount: $
B. Previous Change Orders $
C. This Change Order $
D. New contract amount $
II. OFFSITE WORK SUMMARY
(Total cumulative dollar amount of all offsite work may not exceed $100,000)
A. Amount of this CO that is for offsite work: $
B. Total cumulative amount of all offsite work after this CO: $
III. SCHEDULE SUMMARY
A. Original contract start date
B. Original completion date
C. Duration of original contract (calendar days)
D. Previously adjusted completion date
E. Number of days the contract will be extended by this CO:
F. The date of Substantial Completion as of this CO:
IV. ACCOUNT ALLOCATIONS
Account Number: $
Account Number: $
Account Number: $
Account Number: $
Account Number: $
Account Number: $
Amount of this Change Order: $
12/2/2022
6,750,869.00
0.00
0.00
7/1/2019
12/2/2022
1250
12/2/2022
0
C0107500.689000 6,350,000.00
C0105410.689000 400,869.00
28,100,182.00
6,750,869.00
80,413,726.00
45,562,675.00
6,750,869.00
Page 2 of 3
+ 0&$**1"(+,"
5.K.e
Packet Pg. 526 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
Request Date:
Contract Information
10371 (CCS)2
Hathaway Dinwiddie Construction
City Yards Modernization - Package A SP2396
PROPOSED CHANGES: See Exhibit A for details.
Project Manager:Sebastian Felbeck Division:Architecture Services
City of Santa Monica 9/2/21
CHANGE ORDER
Contract # Change Order (CO) # Council Approval Date:4/27/21
Contractor: Contractor's Vendor #360339
Project: Project #
V. APPROVALS
Date Date
Date Date
Date
OPTIONAL - Client Department Representative
FUNDS AVAILABILITY CERTIFICATION:
Date
#DIVISIONHEAD #PWDIRECTOR
#CLIENTDEPARTMENT
#FINANCE
The signing of a Change Order indicates that the parties have reached a full resolution, settlement and
accord, and satisfaction with respect to all claims for cost and extensions of time that were asserted, or
that could have been asserted, whether known or unknown at the time of execution of the Change Order,
and that are related to the subject matter of the Change Order, including without limitation all claims,
costs or damages for delay, disruption, hindrance, interference, extended or extraordinary direct and
indirect overhead, multiplicity of Changes, loss of productivity labor or material cost escalations,
inefficiency, the "impact" of the Change on the Work, legal expenses, consultant costs, interest, lost profits
or revenue, bond or insurance costs, currency fluctuations, changes in taxes or other related claims, costs
or damages, and all Compensable Delay costs associated with this change.
#PM #CONTRACTOR
Page 1 of 3
+ 0&$**1"(+,"
"./&*"(" '
-+*./-0 /&+**$"-
/%23&*2&!!&"+*./-0 /&+*
-& "-".&!"*/
,&/(-+$-)$-
%-&./+,%"-&.%(&,
/&*$&-" /+-+#0(& +-'.
& '(/"
-+ 0-")"*/*$"-
- "(&.,-4
5.K.e
Packet Pg. 527 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
Request Date:
Contract Information
10371 (CCS)3
Hathaway Dinwiddie Construction
City Yards Modernization - Package A SP2396
PROPOSED CHANGES: See Exhibit A for details.
Contractor:Contractor's Vendor #360339
Project:Project #
City of Santa Monica 3/7/22
CHANGE ORDER
Contract #Change Order (CO) #Council Approval Date:10/12/21
Project Manager:Sebastian Felbeck Division:Architecture Services
CHANGE ORDER AMOUNT $
I.CONTRACT SUMMARY
A.Original contract amount:$
B.Previous Change Orders $
C.This Change Order $
D.New contract amount $
II.OFFSITE WORK SUMMARY
(Total cumulative dollar amount of all offsite work may not exceed $100,000)
A.Amount of this CO that is for offsite work:$
B.Total cumulative amount of all offsite work after this CO:$
III.SCHEDULE SUMMARY
A.Original contract start date
B.Original completion date
C.Duration of original contract (calendar days)
D.Previously adjusted completion date
E.Number of days the contract will be extended by this CO:
F.The date of Substantial Completion as of this CO:
IV.ACCOUNT ALLOCATIONS
Account Number:$
Account Number:$
Account Number:$
Account Number:$
Account Number:$
Account Number:$
Amount of this Change Order:$
34,851,051.00
3,300,000.00
83,713,726.00
45,562,675.00
3,300,000.00
C0105410.689720 3,000,000.00
C0104580.689000 200,000.00
01500020.52914C 100,000.00
12/2/2022
3,300,000.00
0.00
0.00
7/1/2019
12/2/2022
1250
12/2/2022
0
Page 1 of 3
DocuSign Envelope ID: 7D119C48-BCFC-45FF-8884-643C23F7D735 5.K.e
Packet Pg. 528 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
Request Date:
Contract Information
10371 (CCS)3
Hathaway Dinwiddie Construction
City Yards Modernization - Package A SP2396
PROPOSED CHANGES: See Exhibit A for details.
Contractor:Contractor's Vendor #360339
Project:Project #
City of Santa Monica 3/7/22
CHANGE ORDER
Contract #Change Order (CO) #Council Approval Date:10/12/21
Project Manager:Sebastian Felbeck Division:Architecture Services
V.APPROVALS
Date Date
Sr. Construction Manager HDCC Sr. Vice President
Date Date
Capital Program Manager Director of Public Works
FUNDS AVAILABILITY CERTIFICATION:
Date
Christopher Dishlip Rick Valte
Araceli Esparza
The signing of a Change Order indicates that the parties have reached a full resolution,settlement and
accord,and satisfaction with respect to all claims for cost and extensions of time that were asserted,or that
could have been asserted,whether known or unknown at the time of execution of the Change Order,and
that are related to the subject matter of the Change Order,including without limitation all claims,costs or
damages for delay,disruption,hindrance,interference,extended or extraordinary direct and indirect
overhead,multiplicity of Changes,loss of productivity labor or material cost escalations,inefficiency,the
"impact"of the Change on the Work,legal expenses,consultant costs,interest,lost profits or revenue,
bond or insurance costs,currency fluctuations,changes in taxes or other related claims,costs or damages,
and all Compensable Delay costs associated with this change.
Sebastian Felbeck Rashmi Metta
Page 2 of 3
DocuSign Envelope ID: 7D119C48-BCFC-45FF-8884-643C23F7D735
3/22/2022 3/22/2022
3/22/2022 3/22/2022
3/31/2022
5.K.e
Packet Pg. 529 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 530 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)
5.K.e
Packet Pg. 531 Attachment: Contracts (5759 : Mod 6 - City Yards Modernization Construction Contract)