Recommended Action
Staff recommends that the City Council:
1. Adopt the attached resolution to accept the regional fund transfer of Safe, Clean
Water (Measure W) funds from the County of Los Angeles Flood Control District;
2. Authorize the City Manager or designee to negotiate and execute agreements to
receive the funds; and
3. Authorize budget changes as outlined in the Financial Impacts & Budget Actions
section of this report.
Summary
The Safe, Clean Water (SCW) Program was approved by Los Angeles County voters
on November 6, 2018. The SCW Program, also referred to as Measure W, authorized
the Los Angeles County Flood Control District (District) to levy a special tax annually on
parcels within the District, which includes the City of Santa Monica. The funds collected
are used for the implementation and maintenance of stormwater infrastructure projects.
Under the SCW Program, 50% of the funds are allocated to regional projects, 40% are
allocated to municipalities as local return, and 10% are allocated to the District for
administration. The funds for regional projects are awarded through a competitive grant
application process. The City submitted a grant application to the District for the
Sustainable Water Infrastructure Project (SWIP) and was awarded $7.5 million over the
next three fiscal years. Staff recommends that City Council adopt the attached
resolution (Attachment A) authorizing the City Manager to execute the necessary
agreements with the District to accept the regional fund transfers.
3.D
Packet Pg. 139
2 of 4
Discussion
Staff submitted a grant request application for SWIP to the Los Angeles County Flood
Control District (District) on December 15, 2019 requesting $7.5 million of regional
program funds from the District’s Safe, Clean Water Program. Numerous agencies
submitted a total of ten applications for Infrastructure Program funding and the District
preliminarily ranked nine infrastructure projects to continue through the scoring process.
As the scoring process unfolded over several meetings, SWIP remained in the pool of
potentially funded projects. On October 13, 2020, the Los Angeles County Board of
Supervisors approved the final list of approved grant applications and SWIP was
awarded $7.5 million.
The SWIP project will construct a new 1.5 million gallon capacity harvesting tank for
stormwater and urban runoff collection and a new 1 million gallon-per-day production
capacity advanced water treatment facility to treat a combination of wastewater and
stormwater for non-potable reuse (e.g. irrigation, toilet flushing) and groundwater
recharge. SWIP will also upgrade the existing Santa Monica Urban Runoff Recycling
Facility with a new reverse-osmosis process to treat urban runoff and stormwater for
non-potable reuse and groundwater recharge. The total SWIP project budget of $95.9
million remains unchanged at this time.
The SCW Program grant funds of $7.5 million would replace existing funding of $7.5
million in budgeted construction costs at the Clean Beach and Ocean Parcel Tax (16),
Wastewater (51), and Stormwater (52) Funds over the next three fiscal years. The
overall scope and cost of the SWIP Project has not increased; the SCW Program grant
would allow the City to implement similar water quality improvement projects in the
future or reduce debt obligation. The grant would be disbursed in $2.5 million
increments over three fiscal years: FY 2020-21, FY 2021-22, and FY 2022-23.
The City Council previously authorized the City Manager to execute an agreement to
receive the annual transfer of municipal funds from the Safe, Clean Water Program.
Those funds are disbursed annually and not through a competitive, one-time grant
process.
3.D
Packet Pg. 140
3 of 4
Past Council Actions
Meeting Date Description
09/10/19
(Attachment B)
Approval of the SWIP design/build contract guaranteed
maximum price amendment
08/25/20
(Attachment C)
Resolution to accept the annual municipal fund transfer from
the SCWP
Financial Impacts and Budget Actions
Staff seeks authority to accept a grant from Los Angeles County Flood Control District’s
Safe, Clean Water Program, appropriate funding, and recommends the following budget
changes.
FY 2020-21 Grant Budget Changes
Establish Revenue Budget Appropriate Funds
Account Number Amount Account Number Amount
16500001.405681 $2,500,000 C1606950.689280 $2,500,000
Total $2,500,000 Total $2,500,000
An equivalent reduction in Capital Improvement Program budgets appropriated at
accounts in the Clean Beach and Ocean Parcel Tax (16), Wastewater Funds (51) and
Stormwater (52) Funds would occur once the grant award is received. Grant funds
received in future fiscal years would be appropriated during their respective Council
budget adoptions.
Prepared By: Curtis Castle, Principal Civil Engineer
Approved
Forwarded to Council
3.D
Packet Pg. 141
4 of 4
Attachments:
A. September 10, 2019 Staff Report
B. Resolution 11281
C. Proposed Resolution
3.D
Packet Pg. 142
City Council Report
City Council Meeting: September 10, 2019
Agenda Item: 8.A
1 of 13
To: Mayor and City Council
From: Susan Cline, Director, Public Works, Engineering and Street Services
Subject: Approval of the Sustainable Water Infrastructure Project (SWIP) Design/Build
Contract Guaranteed Maximum Price Amendment
Recommended Action
Staff recommends that the City Council:
1. Authorize the City Manager to negotiate and execute a Guaranteed Maximum
Price amendment to Design-Build Agreement No. 10736 (CCS) in the amount
not to exceed $84,973,490 (including $6,050,000 City contingency) with Kiewit
Infrastructure West Co., a Delaware-based company, for the construction phase
of the Sustainable Water Infrastructure Project for the Public Works Department
for a new total amount not to exceed $92,473,490.
2. Authorize the Director of Public Works to issue any necessary change orders and
contract modifications to complete additional work within the contract authority.
3. Authorize the City Manager to negotiate and execute a first modification to
Professional Service Agreement No. 10541 (CCS) in the amount of $1,090,080
with Stantec Consulting Services, an Edmonton, Canada-based company, to
provide additional owner’s engineer services and construction inspection
services for the Public Works Department. This will result in a five-year
agreement with a new total amount not to exceed $2,740,000, with future year
funding contingent on Council budget approval.
4. Authorize the City Manager to accept and execute the amended funding
agreement and all necessary documents to increase the funding from the State
Water Board Clean Water State Revolving Fund Program in the amount of
$19,000,000 and to accept all renewals.
5. Adopt the attached resolution authorizing the application for an additional
$19,000,000 in funding from the State Water Board Clean Water State Revolving
Fund Program.
6. Adopt the attached resolution for Reimbursement Resolution and Pledged
Revenue and Fund(s).
7. Authorize the Director of Public Works, as the City’s Authorized Representative
pursuant to State Water Board requirements, to issue any
necessary amendments to the Clean Water State Revolving Fund
agreement within contract authority.
8. Authorize the budget changes as outlined in the Financial Impacts & Budget
Actions section of this report.
3.D.a
Packet Pg. 143 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
2 of 13
Summary
The City has supplied safe and reliable water service to its residents and businesses for
more than 100 years. To ensure the continued safety, reliability and affordability of that
service, the City’s Sustainable Water Master Plan was updated in 2018, with the goal of
achieving water self-sufficiency by 2023. This goal will be reached through a
combination of water demand reduction strategies and increased development of local
water supplies. Water self-sufficiency will result in long-term cost protection for
ratepayers, a drought resilient local water supply, and a reduced energy footprint
resulting from the elimination of water delivery from distant locations.
As a key strategy to achieve water self-sufficiency, the implementation of the
Sustainable Water Infrastructure Project (SWIP) would supply 1,680 acre-feet per year
(AFY) of clean and reliable water, which represents about 12% of the City’s annual
water demand. The SWIP leverages alternative water resources by treating brackish
(salty) groundwater, stormwater, and municipal wastewater for non-potable reuse and
groundwater recharge.
The City awarded a design build agreement to Kiewit Infrastructure West Co. (Kiewit) to
provide design services for the SWIP and subsequently submitted a Guaranteed
Maximum Price (GMP) for construction services. Staff recommends executing a GMP
amendment in the amount not to exceed $84,973,490 (including $6,050,000 City
contingency) for a total contract amount not to exceed $92,473,490. This represents a
significant increase over the project’s original estimates, primarily due to the rapid rise in
regional public works construction costs.
The City also awarded a professional services agreement to Stantec to provide Owner’s
Engineer services that included engineering oversight and advisory services throughout
the design phase. With the construction phase now fully defined, staff recommends
executing a modification in the amount of $1,090,080 for construction inspection and
support services during the construction phase for a total contract amount not to exceed
$2,740,000.
3.D.a
Packet Pg. 144 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
3 of 13
After value engineering and negotiating based on a submittal from the Design Build
team in May 2019, the total estimated cost for the Project as recommended by staff
is now $95.9 million. This is roughly $26 million over the current budget of $69.9
million approved in 2016. The total estimated cost includes $720,000 for
administrative costs including permitting, public outreach, and prevailing wage
services. Staff recommends that Council approve an additional $19 million loan
financed through the existing Clean Water State Revolving Fund (CWSRF) and an
additional $7 million budget appropriation as detailed below.
Discussion
The City’s Sustainable Water Master Plan (SWMP) outlines a comprehensive plan to
achieve water self-sufficiency by 2023. The SWMP seeks to reduce the City’s reliance
on imported water, develop local groundwater resources, and integrate available local
water resources by treating brackish (salty) groundwater, municipal wastewater, and
wet and dry weather runoff. The Sustainable Water Infrastructure Project (SWIP) would
harvest these water sources and treat them for non-potable uses such as irrigation,
toilet flushing, and recharging the City’s groundwater supply as shown in Figure 1. The
SWIP would be a first-of-its-kind, innovative and progressive Advanced Water
Treatment Facility (AWTF) to be permitted in California for groundwater recharge.
3.D.a
Packet Pg. 145 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
4 of 13
Figure 1: SWIP Overview
The SWIP is a major component of the SWMP as it would provide a sustainable and
drought resilient water resource in its production of advanced treated water for recharge
to local groundwater aquifers. This aquifer recharge would then provide the City with an
increased raw water supply that could then be treated with the implementation of a
second major component of the SWMP: the future Arcadia water treatment plant
expansion.
As depicted in Figure 1, the SWIP consists of an underground AWTF and stormwater
harvesting tank at the Civic Center surface parking lot, and facility enhancements to the
existing Santa Monica Urban Runoff Recycling Facility (SMURRF). Preliminary
renderings of the initial concept design are shown in Attachment A. The AWTF would
produce 1.0 million gallons per day (MGD) of purified water by treating harvested runoff
in the tank and municipal wastewater diverted from the city wastewater system, which
would offset imported water purchases from Metropolitan Water District (MWD). The
tank (the size of more than 2 Olympic sized pools) would have the capacity to harvest
1.5 million gallons (MG) of dry-weather runoff and wet-weather (stormwater) runoff.
Reverse osmosis membrane filtration upgrades and other enhancements to the
3.D.a
Packet Pg. 146 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
5 of 13
SMURRF would allow it to operate at full production and produce 0.5 MGD of treated
water. In total, the SWIP would supply 1,680 acre-feet per year (AFY) of treated water.
Beneficial Use
Besides the increased water supply capacity, the SWIP provides multiple benefits that
include reducing urban runoff discharges to the ocean, improving beach water quality in
the Santa Monica Bay by reducing the amount of polluted water entering the Bay,
advancing compliance with the MS4 permit and Enhanced Watershed Management
Program (EWMP) requirements, and generating a new water resource. The EWMP is a
City stormwater planning program implemented in order to achieve the State’s MS4
permit. The MS4 permit is a State permit regulating discharge water quality for any
water that enters navigable waters. In addition, the SWIP would implement new Civic
Center surface parking lot improvements and enhance access to the adjacent childcare
center and sports field.
Project Costs
The approved $69.9 million budget was developed based on estimates supported by
preliminary information available in 2016. As the design progressed and the detailed
construction scope of the various project elements were more fully defined, the
estimated project costs increased and resulted in an initial GMP of $110.9 million in May
of 2019. Staff was able to reduce the scope and estimate to $92.4 million for a project
total of $95.9 million (including City’s costs such as inspection services and permitting
costs). The higher costs are associated to trending increases in the regional water
production market, shortage of highly skilled labor, volatile material prices, and a large
volume of projects in the Los Angeles region.
With this significant increase in estimated project cost, staff evaluated three options for
next steps: proceed with a reduced scope, do not build, or re-bid with a reduced scope.
The evaluation of options is summarized in Table 1.
Return on Investment
3.D.a
Packet Pg. 147 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
6 of 13
While the SWIP requires a significant upfront capital expenditure, the cost would be
offset by treating and producing more water locally, allowing the City to avoid costly
imported water fees and wastewater fees paid to outside agencies.
Staff conducted a financial analysis comparing future costs of imported water and
avoided wastewater treatment fees against the projected cost of locally produced
water over a 35-year period. The analysis supported the financial viability of the SWIP
even at the $110 million price. The project’s life expectancy of approximately 50 years
well exceeds the 35-year ROI (return on investment).
Proceeding with the SWIP as proposed is critical to the City’s effort to achieve water
self-sufficiency by 2023. Residents and business owners within the City would benefit
from the implementation of SWIP by keeping local water costs lower than without the
project compared to the ongoing cost increases for imported water.
SWIP also represents a major step forward in the City’s effort to meet the requirements
of the City’s stormwater discharge permit (MS4). Non-compliance with the MS4 permit
requirements may subject the City to future penalty assessments ranging between
$1,000 and $10,000 or more per day during a rain event beginning in 2021, which is the
deadline for agencies to comply with their Enhanced Watershed Management Plans.
3.D.a
Packet Pg. 148 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
7 of 13
Table 1. Next Step Options
Option Cost Pros Cons
1. Proceed
with
reduced
scope
(storage
tank is
reduced to
1.5MG
from the
original
4.5MG)
$95.9M • EWMP is partially
implemented.
• Achieving water self-
sufficiency remains on
schedule
• Cost is fair and
reasonable in today’s
current market
• Project sees a return on
investment over a 35-
year period.
• Reduce pollutants to
ocean improving ocean
water quality.
• $69.9M budgeted. $26M budget
shortfall.
2. No Build $9M • Least costly option.
• No construction
impacts to public.
• Water self-sufficiency not
achieved by 2023
• Continue purchasing costly
imported water at $1.8 million
per year in 2022 (2022
completion), plus annual rate
increases
• $1.1 million in sewer costs per
year in 2021, plus annual rate
increases
• Loss of $56.9M low interest
(1.8%) CWSRF loan with $4.0
million forgiveness, with no
guaranteed funding for alternate
projects
• Loss of $9 million in already-
spent design funds with no
project
3. Re-bid with
a reduced
scope
$9M + X • May result in better
pricing due to
competition
• EWMP is partially
implemented.
• First major step in water
self-sufficiency
Preserve low interest
loan
• Stormwater funding
supports the project.
• Project sees a return on
• No guarantee of improved bids,
current pricing was validated and
reasonable in current market.
• High risk of incurring price
escalation or higher cost.
• Significant schedule delay (at
least 1 year would be necessary
to revise the financing agreement,
prepare the revised bid package,
complete procurement, and
negotiate the new contract).
• Additional construction impacts to
3.D.a
Packet Pg. 149 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
8 of 13
investment over a 35-
year period.
• Reduce pollutants to
ocean improving ocean
water quality.
the users after Early Child Lab
School and Sports Field are
completed.
Staff recommends Option 1, for a total project cost of $95.9 million.
Table 2 provides a comparison of the original budget and the proposed budget. The
proposed budget examines the project moving forward with Option 1, the reduced
scope, 1.5MG tank option. This option requires an additional $26 million in budget, $19
million of which would come from an increase to the CWSRF loan. Staff has
communicated with the State regarding the loan increase and the State has confirmed
funds are available for the SWIP. The State would confirm the final loan approval upon
receiving the City Council Resolution. The execution of the GMP is contingent upon
receiving the increased CWSRF loan. The increased loan amount to fund the SWIP is
already included in the proposed Wastewater Fund rate adjustment scenarios
presented to Council at the August 13, 2019 Council Water/Wastewater Rate Study
Session. Staff is not seeking for any additional budget increases than what was already
presented to Council at the Study Session. Should the proposed Wastewater Fund rate
adjustment not be approved, capital projects and operating budgets in the Wastewater
Fund would need to be reduced by approximately $13 million over the next 5 years to
cover the increased SWIP cost covered by the Wastewater Fund. Potential cuts would
include forgoing certain maintenance activities and deferring the annual wastewater
main replacement program during that period. While there is always some risk in
reducing maintenance activities and deferring capital improvements, the cuts would be
to the wastewater system on non-pressurized pipes, which are less subject to breaks
and leaks than the pressurized potable system. The cuts would not impact potable
water infrastructure. Proposed budget increases are detailed by fund in table 2 and in
the financial section.
3.D.a
Packet Pg. 150 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
9 of 13
Table 2: Original Project Funding Sources vs. Proposed Project Funding Sources
Fund Type Original Funding
Sources
Increase Proposed
Funding Sources
State Loan $56.9M $19.0M $75.9M
Measure V $4.5M $3.1M $7.6M
Storm Water Fund $1.4M $1.4M
Wastewater Fund $7.1M $7.1M
Stormwater In Lieu
Fees1
$3.0M $3.0M
Development
Agreement fees
related to City storm
water infrastructure
$0.9M $0.9M
Total $69.9M $26.0M $95.9M
1 Fees paid to the City by applicants (those obtaining a building permit) in lieu of installing permanent stormwater
collection or infiltration devices
Schedule
Construction is tentatively scheduled to start in November of 2019 and take
approximately 2.5 years to complete.
Public Outreach
Public Outreach will be conducted by City staff and Kiewit. The outreach team will meet
regularly with neighboring businesses and residents to keep them informed of the
project schedule and construction impacts. The project was presented to the Task
Force on the Environment subcommittee on August 19, 2019. The subcommittee
supports the SWIP and moving forward with Option 1.
Permitting
This project will require multiple permits which include, but are not limited to, California
Coastal Commission, Building and Safety (for surface improvements), and the Regional
3.D.a
Packet Pg. 151 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
10 of 13
Water Quality Control Board with the Division of Drinking Water. Kiewit would pursue
and obtain all necessary permits.
Environmental Analysis
The California Environmental Quality Act (CEQA) Mitigated Negative Declaration, the
Mitigation Monitoring and Reporting Plan, and the National Environmental Policy Act
(NEPA) documents for the project were certified by the Santa Monica City Council on
September 27, 2016, and the Notice of Determination was filed at the State
Clearinghouse on September 30, 2016. An addendum to the Mitigated Negative
Declaration was also prepared in October 2018 to reflect the change and is provided as
Attachment B.
Past Council Actions
12/6/16 (Attachment C) Adoption of Reimbursement Resolution and Pledged
Revenue and Fund(s) Resolution for the Sustainable
Water Infrastructure Project
01/26/16 (Attachment D) Authorizing to Accept the Funding Agreement from
State Water Resources Control Board for Sustainable
Water Infrastructure Project
08/28/18 (Attachment E) Selection and Award of Sustainable Water
Infrastructure Project Design/Build Services Contract
11/27/18 (Attachment F) Sustainable Water Master Plan Update and Pathway to
Water Self-Sufficiency.
Financial Impacts and Budget Actions
Approval of the recommended action requires the following:
1. Modification to the State Water Resources Control Board (SWRCB) Funding
Agreement (reference to Attachment G, State Water Board loan agreement).
A loan increase of $19,000,000 is required to increase the project budget. Staff
recommends Council to authorize a resolution to apply for the modification
increasing the loan amount and to adopt the Reimbursement Resolution and
3.D.a
Packet Pg. 152 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
11 of 13
Pledged Revenue and Fund(s) Resolution. The State has confirmed the additional
funding is available to be allocated to SWIP. Upon adoption of the resolution, staff
would begin the administrative process of application and execution for an updated
loan agreement with the State.
The annual debt service on the additional $19 million in loan proceeds, which totals
approximately $835,000, will be shared by the Clean Beaches and Ocean Parcel
Tax (16) Fund and the Wastewater (51) Fund. The 16 Fund will pay debt service on
$6 million of the loan and the 51 Fund will pay debt service on the remaining
$13 million loan amount. The split between the funds for the additional loan amount
is in line with how the rest of project costs are divided, which is based on the
proportional benefits to Water Resources and the Stormwater Program. The debt
service for the additional loan amount will be incorporated in the ten-year forecasts
for both funds with the anticipation that a Wastewater rate increase would be
authorized later in 2019 through the Wastewater rate study.
2. An appropriation of the $13,000,000 State loan amount to the FY 2019-20
Wastewater Fund Capital Improvement Program in account number
C5106950.689000.
3. An appropriation of the $6,000,000 State loan amount to the FY 2019-20 Clean
Beaches and Ocean Parcel Tax Fund Capital Improvement Program in account
number C1606950.689000. Additional appropriation of $3,140,054 from the Clean
Beaches and Ocean Parcel Tax Fund Balance to FY 2019-20 Capital Improvement
Program account number C1606950.689000.
4. An appropriation of $3,000,000 from the Stormwater Fund to FY 2019-20
Stormwater Fund Capital Improvement Program account number
C5206950.689530.
3.D.a
Packet Pg. 153 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
12 of 13
5. An appropriation of $900,000 from the Wastewater Fund from Development
Agreement revenue to FY 2019-20 Capital Improvement Program account number
C5106950.689540
6. An appropriation of $15,840,000 to reflect a transfer from the Wastewater Fund
(account number 51800001.691660) to the Clean Beaches and Ocean Parcel Tax
Fund (account number 16800001.691660) for funds received from the Clean Water
State Revolving Fund.
7. GMP Amendment to Kiewit Design Build Agreement
Staff seeks authority to approve funding from the Wastewater Fund, Clean
Beaches and Ocean Parcel Tax Fund and the Stormwater Fund to increase the
amount of the design/build contract with Kiewit Infrastructure West, Inc. for the
construction phase of the design / build services contract.
Agreement Modification Request
Request Amount
FY 2019-20 Budget
CIP Account #
Total Contract Amount
$33,319,855 C1606950.689000 $33,319,855
$46,353,635 C5106950.689000 $53,853,635
$900,000 C5106950.689540 $900,000
$4,400,000 C5206950.689000 $4,400,000
$84,973,490 Total $92,473,490
8. First Modification to Owner’s Engineer Professional Service Agreement
Staff seeks authority to approve funding from the Wastewater Fund to increase the
amount of the contract with Stantec for construction inspection and support
services during the construction phase.
Agreement Modification Request
Request Amount
FY 2019-20 Budget
CIP Account # Total Contract Amount
$1,090,080 C5106950.689000 $2,740,000
3.D.a
Packet Pg. 154 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
13 of 13
Prepared By: Jason Hoang, Civil Engineering Associate
Approved
Forwarded to Council
Attachments:
A. SWIP Renderings
B. Addendum to MND- SWIP October 2018
C. December 6, 2016 Staff Report - Adoption of Reimbursement Resolution and
Pledged Revenue and Fund(s) for SWIP
D. January 26, 2016 Staff Report - Application for CWSRF Funding
E. August 28, 2018 Staff Report - Selection and Award of Design/Build Services
Contract
F. November 27, 2018 Staff Report - Sustainable Water Master Plan Update and
Pathway to Water Self-Sufficiency
G. California Clean Water State Revolving Funding Agreement for SWIP September
2017
H. Stantec Oaks Initiative Disclosure Form
I. Kiewit Oaks Initiative Disclosure Form
J. PW - Resolution - SWIP Grant - 09.10.2019
K. PW - Resolution - SWIP 2 Pledge - 09.10.2019
L. Written Comment
M. PowerPoint Presentation
3.D.a
Packet Pg. 155 Attachment: September 10, 2019 Staff Report (4336 : Adopt Resolution to Accept Measure W Grant Funds)
City Council Meeting: August 25, 2020 Santa Monica, California
RESOLUTION NUMBER 11281 (CCS)
(City Council Series)
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF SANTA MONICA TO RECEIVE THE ANNUAL TRANSFER OF
FUNDS FROM THE LOS ANGELES COUNTY FLOOD CONTROL DISTRICT FOR
THE SAFE, CLEAN WATER PROGRAM (MEASURE W)
WHEREAS, Measure W, also known as the Safe, Clean Water (SCW) Program,
was passed by Los Angeles County voters on November 6, 2018, and authorized the Los
Angeles County Flood Control District (the “District”) to levy a special tax annually on
parcels within the District, which encompasses cities and unincorporated areas of the
County, beginning with fiscal year 2019-20, and continuing until ended by the voters; and
WHEREAS, the District, pursuant to the Los Angeles Region Safe, Clean Water
(“SCW”) Program ordinance (Chapter 16 of the Los Angeles County Flood Control District
Code) and the SCW Program Implementation Ordinance (Chapter 18 of the Los Angeles
County Flood Control District Code), administers the SCW Program for the purpose of
funding projects and programs to increase stormwater and urban runoff capture and
reduce stormwater and urban runoff pollution in the District; and
WHEREAS, pursuant to Section 16.04.A.2. of the Los Angeles County Flood
Control District Code, forty percent (40%) of annual SCW Program tax revenues must be
allocated to municipalities within the District, in the same proportion as the amount of
revenues collected within each municipality, to be expended by those cities within the
cities' respective jurisdictions and by the County within the unincorporated areas that are
DocuSign Envelope ID: 25AD0B37-527D-4922-A4B6-32C728A67F51
3.D.b
Packet Pg. 156 Attachment: Resolution 11281 (4336 : Adopt Resolution to Accept Measure W Grant Funds)
2
within the boundaries of the District, for the implementation, operation and maintenance,
and administration of Projects and Programs, in accordance with the criteria and
procedures established in Chapters 16 and 18 of the Los Angeles County Flood Control
District Code; and
WHEREAS, pursuant to Section 16.05.A.1. of the Los Angeles County Flood
Control District Code, prior to their receipt of SCW Program funds, municipalities must
enter into an agreement with the District to transfer SCW Program funds; and
WHEREAS, the County of Los Angeles Board of Supervisors has approved a
standard template agreement (the “Agreement”), as required by and in accordance with
Section 18.09 of the Los Angeles County Flood Control District Code, for the transfer of
SCW Program funds to municipalities; and
WHEREAS, the City of Santa Monica is eligible to receive an estimated Eight
Hundred and Ten Thousand Dollars ($810,000) in SCW Program funds in Fiscal Year
2020-21 and subsequent fiscal years; and
WHEREAS, in Fiscal Year 2020-21 and subsequent fiscal years, the City’s receipt
of SCW Program funds will enable the City to continue essential maintenance of
stormwater infrastructure and to plan future stormwater projects;
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND BY
THE CITY COUNCIL OF THE CITY OF SANTA MONICA, STATE OF CALIFORNIA, AS
FOLLOWS:
SECTION 1. The foregoing recitals are true and correct.
SECTION 2. The City Manager is authorized to execute the Agreement to receive
SCW Program funds from the District.
DocuSign Envelope ID: 25AD0B37-527D-4922-A4B6-32C728A67F51
3.D.b
Packet Pg. 157 Attachment: Resolution 11281 (4336 : Adopt Resolution to Accept Measure W Grant Funds)
3
SECTION 3. The SCW Program funds received by the City in Fiscal Year 2020-21
and subsequent fiscal years will be appropriated to the revenue account
16500003.402090.
SECTION 4. The City Clerk shall certify to the adoption of this Resolution, and
thenceforth and thereafter the same shall be in full force and effect.
APPROVED AS TO FORM:
_____________________
GEORGE S. CARDONA
Interim City Attorney
DocuSign Envelope ID: 25AD0B37-527D-4922-A4B6-32C728A67F51
3.D.b
Packet Pg. 158 Attachment: Resolution 11281 (4336 : Adopt Resolution to Accept Measure W Grant Funds)
Adopted and approved this 25th day of August 2020.
__________________________
Kevin McKeown, Mayor
I, Denise Anderson-Warren, City Clerk of the City of Santa Monica, do hereby
certify that Resolution No. 11281 (CCS) was duly adopted at a meeting of the Santa
Monica City Council held on the 25th day of August 2020, by the following vote:
AYES: Councilmembers Himmelrich, Davis, Jara, McCowan, Winterer
Mayor Pro Tem O’Day, Mayor McKeown
NOES: None
ABSENT: None
ATTEST:
_____________________________________
Denise Anderson-Warren, City Clerk
DocuSign Envelope ID: 25AD0B37-527D-4922-A4B6-32C728A67F51
3.D.b
Packet Pg. 159 Attachment: Resolution 11281 (4336 : Adopt Resolution to Accept Measure W Grant Funds)
1 City Council Meeting: December 15, 2020 Santa Monica, California RESOLUTION NUMBER (CCS) (City Council Series) A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SANTA MONICA TO RECEIVE THE ANNUAL TRANSFER OF FUNDS FROM THE LOS ANGELES COUNTY FLOOD CONTROL DISTRICT FOR THE SAFE, CLEAN WATER PROGRAM (MEASURE W) WHEREAS, Measure W, also known as the Safe, Clean Water (“SCW”) Program, was passed by Los Angeles County voters on November 6, 2018, and authorized the Los Angeles County Flood Control District (the “District”) to levy a special tax annually on parcels within the District, which encompasses cities and unincorporated areas of the County, beginning with fiscal year 2019-20, and continuing until ended by the voters; and WHEREAS, the District, pursuant to the Los Angeles Region SCW Program ordinance (Chapter 16 of the Los Angeles County Flood Control District Code) and the SCW Program Implementation Ordinance (Chapter 18 of the Los Angeles County Flood Control District Code), administers the SCW Program for the purpose of funding projects and programs to increase stormwater and urban runoff capture and reduce stormwater and urban runoff pollution in the District; and WHEREAS, pursuant to Section 16.04.A.3. of the Los Angeles County Flood Control District Code, fifty percent (50%) of annual SCW Program tax revenues must be allocated to pay for the implementation, operation and maintenance, and the administration of Projects and Programs implemented through the Regional Program, 3.D.cPacket Pg. 160Attachment: Proposed Resolution [Revision 1] (4336 : Adopt Resolution to Accept Measure W Grant Funds)
2 including Projects and Programs identified in approved regional plans such as stormwater resource plans developed in accordance with Part 2.3 (commencing with section 10560) of Division 6 of the Water Code, watershed management programs developed pursuant to waste discharge requirements for municipal separate storm sewer system (MS4) discharges within the coastal watersheds of the County, issued by the Los Angeles Regional Water Quality Control Board, and other regional water management plans, as appropriate, in accordance with the criteria and procedures established by the District Code, with funds allocated to the Regional Program to be distributed among the nine (9) Watershed Areas in proportion to the funds generated in each Watershed Area; and WHEREAS, pursuant to Section 16.05.A.1. of the Los Angeles County Flood Control District Code, prior to their receipt of SCW Program funds, municipalities must enter into an agreement with the District to transfer SCW Program funds; and WHEREAS, the County of Los Angeles Board of Supervisors has approved a standard template agreement (the “Agreement”), as required by and in accordance with Section 18.09 of the Los Angeles County Flood Control District Code, for the transfer of SCW Program funds to municipalities for regional projects; and WHEREAS, the City of Santa Monica is eligible to receive an estimated total of Seven Million Five Hundred Thousand dollars ($7.5M) in SCW Program funds disbursed equally over Fiscal Years 2020-21, 21-22, 23-22 in Two Million Five Hundred Thousand dollar ($2.5M) increments for use for certain stormwater projects; and WHEREAS, in future years the City may apply for and be awarded additional SCW Program funds for different stormwater projects. 3.D.cPacket Pg. 161Attachment: Proposed Resolution [Revision 1] (4336 : Adopt Resolution to Accept Measure W Grant Funds)
3 NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND BY THE CITY COUNCIL OF THE CITY OF SANTA MONICA, STATE OF CALIFORNIA, AS FOLLOWS: SECTION 1. The foregoing recitals are true and correct. SECTION 2. The City Manager or her designee is authorized to execute Agreements and any other related documents including permits and maintenance agreements to receive SCW Program funds from the District. SECTION 3. The SCW Program funds received by the City in Fiscal Year 2020-21 and subsequent fiscal years will be appropriated to the revenue account 16500001.405681. SECTION 4. The City Clerk shall certify to the adoption of this Resolution, and thenceforth and thereafter the same shall be in full force and effect. APPROVED AS TO FORM: GEORGE S. CARDONA Interim City Attorney 3.D.cPacket Pg. 162Attachment: Proposed Resolution [Revision 1] (4336 : Adopt Resolution to Accept Measure W Grant Funds)