SR-06-24-1980-6E7667 1 PUN 2 4 1980 Santa Monica, California, June 19, 1980 TO: Mayor and City Council FROM: City Staff SUBJECT: Supplemental Report - Reconstruction of 3rd Street between Pico Boulevard and Ocean Park Boulevard - Award of Contract Introduction This report recommends the City Council award a contract for the reconstruction of 3rd Street between Pico Boulevard and Ocean Park Boulevard to A.M. Construc- tion, the lowest responsible bidder, in the amount of $145,337.50 Background Bids for the street reconstruction were opened after 3:00 P.M., Wednesday, June 18, 1980, and publicly read by the Deputy City Clerk. Plans and specifications were issued to nine contractors. Four bids were received as follows: A.M. Construction . . . . . . . . . . $145,337.50 Damon Construction Co. . . . . . . . $151,716.50 Security Paving Co. . . . . . . . . . $198,120.00 B - 1 Enterprise Corp. . . . . . . . $226,100.00 City Engineer's Estimate . . . . . . $111,699.50 Estimate of Funds Required Engineering . . . . . . . . . . . . . $ 2,500.00 Construction Contract . . . . . . . $145,337.50 Inspection and Contingencies . . . . $ 22,162.50 Total .$170,000.00 T0: Mayor and City Council -2- June 19, 1980 Community Development Block Grant (CDBG) funds in the amount of $130,000 were budgeted and are available for this project. State Gas Tax funds in the esti- mated amount of $40,000 may be used to supplement the financing of this project. A storm drain system in 3rd Street between Pico Boulevard and Strand Street was recently completed. Due to this construction, portions of the street were re- designed for removal of hazards, such as cross gutters and humps, and increasing curb heights at corners for protection of pedestrians. Curb heights will also be reduced on portions of the easterly side to allow car doors to be opened on parked cars. Wheel chair ramps will be constructed at corners requiring reconstruction. Recommendation It is recommended that the subject contract be awarded to A.M. Construction, the lowest responsible bidder, subject to HUD approval, in the amount of $145,337.50 and that additional funds in the amount of $40,000 be appropriated from unappro- priated Gas Tax funds to complete this project. Prepared by: Stan Scholl Toivo Marjanen , . 7. SUN 2 4 1960 Santa Monica% California; June 13, 1980 TO: Mayor and City Council FROM: City Staff SUBJECT: Reconstruction of 3rd Street Between Pico Boulevard and Ocean Park Boulevard Introduction This report recommends the City Council award a contract for the reconstruc- tion of 3rd Street between Pico Boulevard and Ocean Park Boulevard to the lowest bidder to be named in a supplemental report. Background Bids for the street reconstruction will be opened after 3:00 p.m., Wednesday, June 18, 1980, and will be publicly read by the City Clerk. Estimate of Funds Required Engineering . . . . . . . . . . . $ 2,200 Construction Contract . . . . . . 138,800 Inspection and Contingencies . . 22,000 TOTAL $163,000 Community Development Block Grant (CDBG) funds in the amount of $130,000 were budgeted and are available for this project. State Gas Tax funds in the esti- mated amount of $33,000 may be used to supplement the financing of this project. A storm drain system in 3rd Street between Pico Boulevard and Strand Street was recently completed. Due to this construction, portions of the street were re- SUN 2 4 1980 B T0: Mayor and City Council -2- June 13, 1980 designed for removal of hazards. Curb heights will also be reduced on por- bons of the easterly side to allow car doors to be opened on parked cars. Wheel chair ramps will be constructed at corners requiring reconstruction. Recommendation It is recommended the contract be awarded to the lowest responsible bidder (to be named in a supplemental report) subject to HUD approval, in the amount of their bid and that additional State Gas Tax funds in the estimated amount of $33,000 be appropriated for the construction contract, inspection and contingencies. Prepared by: Stan Scholl Dout McAteer Agenda Item 6 -E7: Presented for consideration was a contract Ear award to A. M. Construction, Inc., for Te cons truce ion of Third Street between Pico and Ocean Park Boulevards in the amount of $14S,337.S0 and a request for an appropriation of $40,000 for contingencies. The staff Greport was presented. Discussion was held. Y o p moved to request staff to report to tie Councrl rn regard to row contingency moneys appropriated have been spent, including in the motion the suggestion of Councilmember Scott that the report be based on the last five projectsin which the project exceeded $50,000. Second by Council- member Scott. Council Vote: Unanimously approved 7 -0 Cowuilmember Reed moved to approve the staff recommendation in regard to the reconstruction of 'third Street between Pico and Ocean Park Bouler-aTd, i.e „ awarding Contract No. 3510 CCS) to A. %L Construction in the amount of $14S,337.S0 and approvin„ an appropriation of $40,000 for contingencies. Second by Councilmember Jennings. Council Tote: Unanimously appraeed 7 -0 CITY COUNCIL MEETING - Jmle 25, 1980 Reference: Contract No. 3510 (CCS)