SR-10-24-1978-6E - 414-001 / 410-0016l OCT 2 4 1978 Santa Monica, California October 10, 1978 TO: Mayor and City Council FROM: City Staff SUBJECT: Grading for the Downtown Shopping Center Introduction This report recommends that the City Council authorize a Change Order to existing Contract No. 3067 (C.C.S.) for the grading and related work for the Downtown Shopping Center in the amount of $106,000. Background In accordance with the Disposition and Development Agreement entered into on September 10, 1975, it is the responsibility of the Santa Monica Redevelopment Agency to convey to the Developer parcels that are clear of all obstructions and ready for construction. Bids for the demolition and some grading work were opened in the City Council Chambers on June 15, 1978. Plans and specifications were issued to over 100 demolition and grading contractors. The Developer prepared the grading plans. The City Staff prepared the demolition plans and the specifications for both phases. M OCT 2 4 1978 To: Mayor and City Council -2- Oct. 10, 1978 As previously reported prior to award of the demolition portion of the work, bids were received as follows: no i i +inn A -1 Lin -Ty Demolition Co. .......... $124,999.00 Maness Excavating & Grading, Inc. .. $164,800.00 Gangi Bilt Homes ................... $175,750.00 Grading Total $46,666.00 $171.665.00 $85,000.00 $249,800.00 $86,750.00 $262,500.00 Harold Morris /J.C. Huggins ......... $155,512.50 $115,392.76 $270,905.26 Cleveland Wrecking Co . ............. $219,845.00 $134,640.00 $354,485.00 City Engineer's Estimate ........... $400,000.00 On July 13, 1978, the City Council authorized a total expenditure of $200,000 and authorized awarding a contract to A -1 Lin -Ty Demolition Co. for the demolition only, for their low bid of $124,999. At that time, the staff recommended that the grading portion of the work in the amount of $46,666 not be awarded because of delays in vacating several of the buildings on the site and unresolved questions relating to details of the grading work and responsibility for certain portions of the cost of the work. Since the award of the contract for the demolition, there have been a number of changes in the grading plans as prepared by the developer and there has been substantial progress in vacating and demolishing the buildings on the site. The contractor, A -1 Lin -Ty Demolition Co. has submitted a revised proposal for the revised work as follows: To: Mayor and City Council -3- Oct. 10, 1978 Original base bid ............................... $ 46,666.00 Differences because of new plan and increases in labor and equipment rates ............. $ 9,333.20 Removal of 15,000 cubic yards of surplus dirt ...... $ 50,000.00 Total $105,999.20 ($106,000) To accomplish this work it will be necessary to approve funds as follows: Grading and Related Work Contract Change -- A -1 Lin -Ty ...................... $106,000.00 Soils Engineering Contract with LeRoy Crandall & Associates .......... $ 20,000.00 Contingencies ....... ............................... $ 25,000.00 Total $151,000.00 Funds have been budgeted in Account No. 01- 200 - 263- 000 -246 (Site Improvements). In addition to the above items of work, there are the substantial amounts of other work which will be performed by City's contractor only upon reimbursement by the developers and /or others. Included in this additional work is the haul -away of approximately 15,000 cubic yards of surplus dirt, and special soils work which may be required on the site of the Broadway Store. These items may total as much as $250,000. It should be noted that staff is planning to use suitable soil on the site to perform all of the required grading. If, during the grading work imported soil is required, additional funding will be requested. Recommendation It is recommended that the Council authorize a Change Order to existing Contract No. 3067 (C.C.S.) be issued for grading and related work to A -1 Lin -Ty Demolition Co. in the amount of $106,000.00 and authorize a total expenditure not to exceed $151,000 for this work, as outlined above. Prepared by: S. Scholl E. D. McAteer J. Jalili J. Hemer Agend' .Item 6 -E: Presented at this time was a recommendation or d app=al of a Change Order in the amount of $106,000.00 and additional -own funding for a total expenditure not to exceed $151,000.00 for grading and related work for the Downtown Shopping Center being done bylA -1 Lin -Ty Demolition Company under Contract No. 3067(CCS). amount tooexPeedv$151e000a00e order Reed. an Council Vote: Unanimously approved 6 -0 Absent: Mayor Swink CITY COUNCIL MINUTES - OCTOBER 24, 1978