SR-12-10-2013-3CCity Council Meeting: December 10, 2013 Agenda Item: 3 —G To: Mayor and City Council From: Martin Pastucha, Director of Public Works Subject: Professional Services Agreement Modification for Design Services for Pico Branch Library Recommended Action Staff recommends that the City Council authorize the City Manager to negotiate and execute a seventh modification to Professional Services Agreement No. 9180 (CCS) in the amount of $28,215 (includes a 10% contingency) with Koning Eizenberg Architects (KEA), a California -based company, to provide additional construction administration and design services to complete the Pico Branch Library Project. This would result in a new agreement in the amount of $996,153. The term of the agreement will remain at four years and is set to expire on June 30, 2014. Executive Summary On February 23 2010, Council authorized a professional services agreement with KEA to provide design services for the Pico Branch Library in an amount not to exceed $882,590. A seventh modification in the amount of $28,215 is required to provide additional construction administration and design services through the anticipated project completion date in early 2014. This would result in a new agreement in the amount of $996,153. The term of the agreement will remain at four years and is set to expire on June 30, 2014. Background On May 12, 2009, Council approved construction of a new branch library at Virginia Avenue Park. On February 23, 2010, Council awarded Professional Services Agreement No. 9180 (CCS) to KEA for design services for the Pico Branch Library, in an amount not to exceed $882,590. The subsequent four modifications were necessary due to project scope and design changes and were issued within budget authority. On Julv 10, 2012, Council approved a fifth agreement modification with KEA in the total amount of $85,348 for construction administration services as well as design services to incorporate the alternate bid item for a Rainwater Harvesting System for a new modified 1 agreement in the amount of $967,938. A sixth modification was issued to extend the term of the agreement without additional compensation. Discussion The construction administration scope in KEA's agreement was limited to a 12 -month construction period. This scope was subsequently extended by two months in the July 10 2012, approved modification to bring KEA's services in line to the anticipated October 2013 completion of the project. The project has encountered unforeseen conditions and scope changes resulting in the anticipated construction completion date for the Pico Branch Library to be revised from October 2013 to early 2014. A seventh modification to the agreement with KEA is necessary to provide construction administration, design services and project closeout through the extended construction timeline. Financial Impacts & Budget Actions The modification to be awarded to Koning Eizenberg Architects is $28,215, for an amended total not to exceed $996,153. Funds in the amount of $28,215 are available in the FY 2013 -14 Capital Improvement Program budget in account C014032.589000, Pico Branch Library. Prepared by: Tom Afschar, Architect Approved: Forwarded to Council: Martin Pastucha Rod Gould Director of Public Works City Manager 2 Reference: Modification to Agreement No. 9810 (CCS)