sr-042611-3fCity Council Meeting: April 26, 2011 Agenda Item: 3 F To: Mayor and City Council From: Martin Pastucha, Director of Public Works Subject: Contract Modification with Katherine Spitz Associates for the Reed Park Improvements Project Recommended Action Staff recommends that the City Council authorize the City Manager to negotiate and execute a second modification to Contract No. 8674 (CCS) with Katherine Spitz Associates, aCalifornia-based company, in an amount not to exceed $6,000 for a total contract amount of $107,849. Executive Summary Katherine Spitz Associates is currently providing design services for various open space improvements. to Reed Park. The design process, initiated in 2007, addressed underutilized areas of the park, improvements to the landscaped areas between the tennis courts and Miles Playhouse, and park frontage along Wilshire Boulevard. Due to the increased duration and scope of the project, design costs are increasing by $6,000 to a total of $107,849. Background On January 23, 2007, Council approved Contract No. 8674 (CCS) with Katherine Spitz Associates for the design of Reed Park. On September 23. 2008, Council approved the Reed Park improvements design concept and the first contract modification in the amount of $16,764 with Katherine Spitz Associates for additional design services resulting from community workshops. On June 22, 2010, Council awarded a contract with Acon Development Inc. for the construction of Reed Park Improvements. Discussion Reed Park occupies a city block and covers 5.3 acres. It is a widely-used Santa Monica park, with Miles Playhouse, the City's Youth Office, six lighted community tennis courts, 1 community meeting rooms, two heavily used basketball courts, and a children's play area. The following improvements are included in the project: 1) Remove existing rogue court, shuffleboard, and horseshoe area to expand the intensively used children's playground area; 2) Replace existing planting along Wilshire Boulevard park edge with a new planting scheme, including the southeast and southwest corners of the park; and 3) Implement new planting scheme, and improved lighting between Miles Playhouse and the tennis courts. Contract Modification Katherine Spitz Associate's original scope of work included public outreach and park design services. The first modification approved by Council on September 23, 2008 included an additional scope of work based upon feedback received at the public outreach events. This second modification to the contract resulted from unforeseen conditions and scope changes during construction, where several of the project areas needed to be redesigned and additional site visits were required of the designer. The site survey did not properly identify the existing conditions of the project area, including playground dimensions and tree locations, which required redesign to reflect the actual site conditions. In addition, changes were made to the proposed bamboo planting materials and concrete colors. The project is scheduled to be completed in mid-June 2011. 2 Financial Impacts & Budget Actions The contract modification to be awarded to Katherine Spitz Associate is $6,000, for a total of $107,849. Funds are included in the FY2010-2011 budget in account 0010598.589000, Reed Park Facility Improvements. Prepared by: Shawna Schlageter, Architectural Associate Approved: ~~ ~, Martin Pastucha Director of Public Works Forwarded to Council: ~~ ~~ Rod Gould City Manager 3 Reference Amended Contract No. 8674 (CCS).