Loading...
SR-309-000 (17) EPWM: CP: AA: LF: MM; F:\DATA\SPFILES\SP1662\cc1662Pool5.DOC City Council Meeting: December 10, 2002 Santa Monica, California TO: Mayor and City Council FROM: City Staff SUBJECT:Modification to Contract 7978 (CCS) with Swinerton Builders for the Municipal Pool Project Introduction This report recommends that the City Council authorize the City Manager to execute a modification to Contract 7978 (CCS) with Swinerton Builders in the amount of $172,595. Discussion In 1998, the City Council approved plans for the Municipal Pool Complex located at 2225 th 16 Street. The construction was divided into two phases. Phase I, consisting of excavation and utility relocation was completed in September 2000. On April 11, 2000, Council awarded Contract Number 7697 (CCS) for construction of Phase II – Pool, Building and Site improvements to Vahdani Construction Co., In. in the amount of $5,299,777 following a competitive bid process. Work commenced on June 5, 2000. The original completion date of March 31,2001 was extended to July 10, 2001 due to unforeseen site conditions and wetter than usual weather. In January 2001, the City began to receive stop notice claims from subcontractors who had provided labor and materials on the project but asserted they had 1 not been paid by Vahdani. On March 28, 2001, the City served a Notice of Default on Vahdani, who failed to cure any of the defaults within the cure period allowed under the construction contract. Therefore, on April 3, 2001, the City sent notice to the bonding company seeking to invoke the performance bond issued on the project and requesting assurances of timely completion of the Project. In response, the bonding company inspected the work completed to date and solicited bids on the open market from qualified contractors with experience in completing projects in default. The bonding company received three bids, the best bid submitted by Swinerton Builders (“Swinerton”). The bonding company then tendered Swinerton’s bid to the City. On July 10, 2001, Council approved Contract Number 7978 (CCS) with Swinerton Builders for $6.85 Million. On February 12, 2002, an additional $842,585 was encumbered to Swinerton Builders for fiberoptic changes, construction of a turnaround area, and additional work related to pre-existing conditions. Scope changes, actual field conditions and additional work not identified during the bidding phase have necessitated an increase to the approved Swinerton contract and contingency. The original contract amount including contingency was $7,692,585. These changes increased the contractor’s costs by a total of $172,595 to $7,865,180. The amount required to close out the project exceeds the current budget authority by $172,595. Budget/Financial Impact Funds in the amount of $172,595 are available as follows: 2 C01066499.589000 “PMP- Municipal Pool” $97,595 C01066001.589000 “PMP – Basketball Court” $ 75,000 Total Available: $172,595 Funds from the basketball court resurfacing account will be used to cover a portion of these additional costs. Because the courts will be resurfaced in asphalt, rather than concrete, the resurfacing costs are less than anticipated. (Asphalt is less expensive and preferred by the players according to surveys, because it is easier on the knees). Recommendation Staff recommends that the City Council: 1. Authorize the City Manager to execute a contract modification to Contract 7978 (CCS) with Swinerton Builders in the amount of $172,595; and 2. Authorize the City Engineer to issue any necessary change orders to complete additional work within budget authority. Prepared by: Craig Perkins, Director of Environmental and Public Works Management Anthony Antich, P.E., City Engineer Barbara Stinchfield, Director of Community and Cultural Services Lauren Friedman, Senior Architect Miriam Mulder, Architect 3