SR-502-002-04 (7) EPWM: CC:AA:RDB:JC; F:\DATA\SPFILES\SP1884\CC1884(DP).DOC City Council Meeting: August 12, 2003 Santa Monica, California Deleted: ¶ ¶ TO: Mayor and City Council FROM: City Staff SUBJECT: Construction Related Contracts for the FY2002-FY2003 Water Main Replacement Project Introduction This report recommends that the City Council award a contract to P&J Utility Company, the best bidder, in the amount of $1,516,154 for construction of the FY 2002-FY2003 Water Main Replacement Project and approve $228,846 in contingency funds for this contract. This report also recommends the City Council authorize the City Manager to negotiate and execute a professional services agreement with Black & Veatch in an amount not to exceed $170,000 for construction management services for the project and approve $25,500 in contingency funds. Each contract will be paid for from the Water Fund. Background Each year, the City Council appropriates funds to the Water Main Replacement Program. This program replaces water mains based on age, corrosion and capacity demands. Staff also considers coordination with other City projects, such as street resurfacing and sewer projects, in order to minimize impacts to the public. 1 Discussion A Notice Inviting Bids for the construction contract was published on May 8 and 10, 2003 in The Los Angeles Times, California Section and the F. W. Dodge newsletter. Bid packages were requested by eighteen contractors and the City Clerk's office received eight sealed bids, which were publicly opened on June 4, 2003 by the Deputy City Clerk. The bid results were as follows: 1. P&J Utility $1,516,154 2. Cedro Construction, Inc. $1,747,088 3. Majich Bros., Inc. $1,748,551 4. Williams Supply $1,818,731 5. Spiniello Companies $1,852,466 6. W.A. Rasic $1,878,621 7. Valverde $1,911,118 8. Miramontes $2,416,254 City Engineer's Estimate $1,700,000 The best bidder P&J Utility Company supplied the City with the names of previous similar projects including water main replacement projects for the Cities of San Francisco and Beverly Hills. In addition, they have successfully completed water main replacement projects for the City of Santa Monica in 1995 and 1997. 2 City staff contacted the Agencies representing these projects and all respondents reported that the contractor's work quality was very good and that work was completed in a timely and cost efficient manner. Staff also contacted the Center for Contract Compliance and found P&J Utility Company in good standing and capable of handling labor compliance issues. The California Contractor?s State License Board verified that the Contractor's license is active and in good standing. Construction Management A Request for Qualifications for construction management services was issued on May 22, 2003 to pre-qualify firms to provide construction management services to the City of Santa Monica. A panel that included representatives from the Environmental and Public Works Management Department?s Civil Engineering and Architecture and Utilities Divisions interviewed four firms from the pre-qualified list. Cost proposals were solicited from all of the pre-qualified firms. Staff recommends Black & Veatch to provide construction management services for this project. Black & Veatch is currently contracted to manage the City?s Sewer Replacement Projects, SMURRF phase III Recycled Water Main Project and the Virginia Park Expansion Project for the City of Santa Monica. Budget/Financial Impact FUNDS REQUIRED FOR THE CONSTRUCTION CONTRACT Construction Contract $1,516,154 Contingency (15%) $ 228,846 3 Total Required $1,745,000 FUNDS REQUIRED FOR THE CONSTRUCTION MANAGEMENT AGREEMENT Construction Management Agreement $ 170,000 Contingency $ 25,500 Total Required $ 195,500 TOTAL FUNDS REQUIRED $1,940,500 FUNDS ARE AVAILABLE IN THE FOLLOWING ACCOUNTS: C25013602.589000 "Water Main Replacement" $1,404,027 C25013603.589000 "Water Main Replacement" $ 536,473 Total Available: $1,940,500 Recommendation Staff recommends that the City Council: 1. Award a contract to P&J Utility Company, the best bidder, in the amount of $1,516,154 for construction of the FY 2002 - FY 2003 Water Main Replacement Project and approve $228,846 in contingency funds for this contract; 2. Authorize the City Manager to negotiate and execute a professional services agreement with the firm of Black & Veatch. in an amount not to exceed $170,000 for construction management services for the project and approve $25,500 in contingency funds for this contract; and 3. Authorize the City Engineer to issue any necessary change orders to complete additional work within budget authority. Prepared by: Craig Perkins, Director, Environmental and Public Works Mgmt. Dept. Anthony Antich, P.E., City Engineer and Architecture Manager 4 Gil Borboa, P.E., Utilities Manager Dave Britton, P.E., Principal Civil Engineer James Creager, P.E., Civil Engineer 5