Council Meeting, March 17, 1992 Santa Monica, California
To: Mayor and City Council
From: City staff
Subject: Recommendation to Increase Existing Contract Amount to
Steiny and Company Inc. for the construction of Mod1fied
Wheelchair Access Ramps with the Installation of the
Midblock Pedestrian Signal on Main street between
Hollister Avenue and Ocean Park Boulevard
Introduction
This report requests that the City Council increase the existing
contract dollar amount awarded to steiny and Company at the
October 8, 1991 council meeting by $8,000.00 (from $40,000.00 to
$48,000.00, plus contingencies) for the construction of two (2 )
modified wheelchair access ramps to accompany Steiny's installation
of the midblock pedestrian signal on Main Street between Hollister
Avenue and Ocean Park Boulevard (between Public Parking Lot 11 and
commercial development on the east side of Main street).
Discussion
In December 1990, the City Council authorized the installation of
a midblock pedestrian signal on Main street between Hollister
Avenue and Ocean Park Boulevard. The contract for this project was
awarded to steiny and Company, the lowest responsible bidder, on
October 8, 1991 in the amount of $40,000.00 plus $4,000.00 in
contingencies. Due to current disabled persons right-of-way access
requirements and unusual curb height conditions at the site (both
realized after the award of the contract) , the two (2) standard
wheelchair access ramps to be constructed for the project had to be
6 ..../)
M'l!.! -1 - 1-'
11f" !- i .~::,.
------
'" .
redesigned. After receiving bids from several concrete sub-
contractors, steiny and Company realized that they could perform
the work for less money than the sub-contractors' bids.
BUdqet/Financial Impact
Funds required: Contract $40,000.00
Contract Increase 8,000.00
contingencies 4,000.00
New Contract Total $52,000.00
A credit for the original two (2) standard access ramps is included
in the New Contract Total. Funds for the additional cost to
construct the two (2) modified access ramps are available in the
capital improvement account #01-770-416-24188-8918-99139 (Traffic
Signal Improvements).
Recommendation
It is recommended that the city council increase the total contract
amount to Steiny and Company by $8,000.00 to $52,000.00 for the
constructlon of two (2) modified wheelchair access ramps within the
existing contract for the installation of a midblock pedestrian
signal on Main street between Hollister Avenue and Ocean Park
Boulevard.
Prepared by: Paul Berlant, Dlrector of Land Use &
Transportation Management
Ron Fuchiwaki, Clty Parking & Traffic Engineer
Jamal Rahimi, Senior Traffic Engineer
Rocky Nungester, civil Engineering Drafting
Technician
---- - - -