council Meeting, March 22, 1994 Santa Monica, California
TO: Mayor and City council
FROM: City staff
SUBJECT: Recommendation to Award a Contract to Sterndahl
Enterprises, Inc. for striping and Signing
Modifications: Broadway from 26th Street to Centinela
Avenuei 26th Street from Wilshire Boulevard to Colorado
Avenuei Colorado Avenue from Stewart Street to
Centinela Avenue
INTRODUCTION
This report requests that the city council award a contract in
the amount of $23,985.00 to Sterndahl Enterprises, Inc. , the
lowest responsible bidder, for striping and signing modifications
along Broadway, from 26th street to centinela Avenue; 26th
Street, from Wilshire Boulevard to Colorado Avenue; Colorado
Avenue, from Stewart street to Centinela Avenue.
DISCUSSION
In September, 1993, the city Council approved the implementation
of the Mid City Neighborhood Traffic Plan. The plan includes
traffic signal improvements, traffic diverters, turn restrictions
and roadway restriping. Staff is already proceeding with traffic
s1gnal improvements and has completed the upgrades of most of the
signals in the plan area. This contract will restripe 26th
Street, Colorado Avenue and Broadway from two lanes of traffic in
each direction to one lane 1n each direction. The remaln1ng
1 MAR 2 2 199It
& -/C..
.
components of the plan will be installed by city staff in
conjunction with the restriping project. In particular, the
traffic diverters will be installed in a temporary fashion for a
trial period to determine the acceptability and effectiveness of
these measures.
As directed by the Council, notices will be sent to property
owners, tenants and businesses in the plan area prlor to the
start of implementation. Implementation will be completed ln two
phases. Phase I will include the restriping, stop sign and
traffic circle measures. Phase II will include the more
restrictive diverters and turn-restrictions. The two phase
approach was requested by the Mid City traffic committee due to
the earthquake damage to the Santa Monica Freeway. Phase II is
tentatively scheduled to be implemented in the summer. Staff
plans to send two notices for each phase, the first,
approximately one month prior to implementation, and a second
notice approximately one week prior to implementatlon.
Implementation of Phase I is tentatively scheduled to begin the
week of May 2, 1994, and will take approximately one month to
complete. In addition, in conjunction with the plan, staff will
be implementing a "traffic hotline" telephone number for
motorists to call to express their comments. The hotline number
will be posted at key areas in the plan area. The hotline calls
will be directed to a voice mail box and reviewed by staff on a
daily basis. .
2
.
Following the published advertisements, the biddlng package for
the installation of this striping and signing was requested by
three (3) contractors. Two (2) bids were received, and read by
the Deputy City Clerk on February 17, 1994. The bids received
were as follows:
Sterndahl Enterprises, Inc. $ 23,985.00
Orange County striping Services, Inc. $ 34,155.00
Engineering Estimate $ 40,000.00
Staff has checked the references provided by Sterndahl
Enterprises, Inc. , the low bidder, and found their work to be
satisfactory.
BUDGET/FINANCIAL IMPACT
Funds required: Contract $23,985.00
Contingencies (10%) 2,400.00
Contract Total $26,385.00
Funds for this project are budgeted in the "Neighborhood Traffic
Improvements" CIP account, #01-770-415-20091-8900-99270.
RECOMMENDATION
It is recommended that the City Cauncll:
1- Award a contract to Sterndahl Enterprises, Inc. , the lowest
responsible bidder, in the amount of $26,385.00 for the
installation of striping and signing modifications along
3
. .
.
Broadway, from 26th street to centinela Avenue; 26th Street,
from Wilshire Boulevard to Colorado Avenue; Colorado Avenue,
from stewart street to Centinela Avenue; and
2. Authorize the city Traffic Engineer to issue any change
orders necessary to complete additional work to the extent
of funds available in accordance with the Admlnlstratlve
Instruction on Change Orders.
Prepared by: SU2anne Frick, Director of Land Use &
Transportation Management
Ron Fuchiwaki, City Traffic Engineer
Jamal Rahimi, Senior Traffic Engineer
Rocky Nungester, Project Engineer