Santa Monica, California
GS:SES:DA 9/13/88
Council Meeting: September 27, 1988
FROM:
..
Mayor and city council
City Staff
TO:
SUBJECT:
Recommendation to Award a Contract for Accessibility
Modifications at Hotchkiss Park, Virginia Park, the
Beach North of the Pier and various other Locations
Introduction
This report requests that the city council award a contract
for accessibility modifications at Hotchkiss Park, Virginia Park,
the Beach north of the pier and various other locations, to Kevin
Kraus,
the lowest responsible bidder,
in the amount of
$108,921.00.
Background
As
part
of
the
annual
accessibility
modifications
construction contract, staff has designed outside sidewalk and
stairs modifications at Hotchkiss Park, restroom and sidewalk
modifications at Virginia Park including new sidewalks to
existing picnic tables, a beach access ramp to connect the
existing boardwalk north of the pier to the ocean front, and
installation of approximately 52 handicapped wheelchair ramps at
various location throughout the City.
A Notice Inviting Bids was published on August 17 and 18,
1988 in the Evening Outlook and sent to four construction
journals and one minority contracting association.
b-i=-
SEP 2 7 1988
.
.
Bidding packages were issued to six contractors. Two bids
were received, opened and read publicly on September 16, 1988, at
3:00 p.m. by the City Clerk. The bidders and their bids were as
follows:
Kevin Kraus
Ryco Construction, Inc.
$108,921.00
197,791. 00
city Engineer's Estimate:
90,000.00
Kevin Kraus has successfully completed several other projects for
the City including last year's accessibility project.
Budget/Financial Analysis
FUNDS REQUIRED
Contract Amount
contingencies
Total Amount Required
$ 108,921
10,899
$ 119,820
Appropriation authority is available in Account No.
01-720-262-000-951 in the amount of $138,562.00 and Account No.
11-740-521-000-908 in the amount of $14,000.
Recommendations
It is recommended that the City Council:
1. Award a contract for the accessibility modifications
at Hotchkiss Park, Virginia Park, the Beach north of
the Pier and at various other locations to Kevin Kraus,
.-
.
.
the lowest responsible bidder, in the amount of
$108,921; and
2. Authorize the City Engineer to issue any necessary
Change Orders to complete the work in conformance with
the Administrative Instructions.
Prepared by:
stan Scholl, Director of General Services
Desi Alvarez, P.E., city Engineer