SR-6-X (3) .~ :. It GS:SES:JAS Council Meetlng: Aprll 28, 1987 e (p -X '1-;;;'1 ~ '7 Santa Monlca, Californla TO: Mayor and Clty Councll FROM: City Staff SUBJECT: Recommendation to Reject Blds and Authorlze Staff to Readvertlse for the Remodel of the MalO Llbrary Introductlon Th~s report recommends that the C2ty Councll reJect all b2ds and authorlze staff to readvertise for the remodel of the Ma2n Ll.brary. Background At the Apr II 22, 1986, meet:tng Councll d H ected staff to remove all asbestos from and remodel the Main Llbrary to lmprove the efflclency of the work space, provlde addltlonal space wherever posslble for pub12c use, and to restore lnterior f~nlshes. Contracts for asbestos abatement work, mOl/log and lnterim storage of the Llbrary furnlshlngs and stacks, and construction management of these proJects were awarded at the July 29, 1986, meeting. On August 12, 1986, a contract was awarded to A. Quincy Jones and AssOclates, Arch~tects, to deslgn the remodel of the Llbrary. MaJor components of the remodel project include: Relnsulatlon of all supply ducts Remodeled maln entrance lobby New Audio visual area on the second floor - I - f.o-'i- q-;;.~ - V1 . < e It .' Relocat~on of Per~od~cals Depart~ent from the second to f~rst floor Remodeled Technlcal Serv~ces Room Complete reflnishing of inter ~or surfaces. 'l'hlS includes fabric wall coverings in the back of the Aud~torlum, Conference Room, staff room, south wall of offlce on flrst floor, and aisles 10 second floor surroundlng the full helght celling. The eXlstlng wood paneling at main entry and all cablnetry wlll be reflnlshed. All other walls wl11 be painted. New lnter~or Il-jhting system WhlCh includes fluorescent llghtlng in all maln read 109 areas, and recessed flxtures in the Technlcal Servlces Room, Clrculatloo Work Room and staff off~ces. New floor coverlngs which lncludes reslllent floor tile In foyer of Audltorlum in basement, and 1n the Technlcal SerVlces area, and work and storage ar eas on the Second floor. All other areas will be carpeted. All ceillngs on the flrst and second floors and the basement Conference Room w~ll recelve new acoustlcal t~les. Exposed trusses 1n Ma~o Readin3 Room wlll receive plaster and paint. All doors and frames wlll be repa~nted. ~ - 2 - ~ ' e e It should be noted that lt was orlglnally intended that the remodeling would 1nclude rerooflng of the library and the lnstallation of a mezzanine to provlde add1tlonal space. However, these ltems were not included 1n the final plans and specl.ficatlons due to thelr costs as well as the development of some al ternative space plann1ng proposals which wl1l resul t in the deslred lncreased space utlllzatlon eff1c1ency. The remodel work 15 scheduled to he completed in October, 1987. Maln Llbrary stacks and furnlture currently stored at the Airport and the SDC Buildlng an Colorado Blvd. will be moved back to the Llbrary 1n November and December. It 15 ant1cipated that the Maln Llbrary wlll be opened to the pub11C by ffild-December. A formal openlng will be sCheduled for January. The plans and speclflcat10ns of the Llbrary remodel were completed by the consultlng archltect, A. QUlncy Jones and Assoclates, and reviewed by Clty staff. A Notlce Inv1tlng Blds was pub11shed on March 26th and 27th, 1987, in tne Evenlng Outlook, four constructlon journals, and seven minority assoclat1ons. Plans and speclflcatlons were lssued to twelve contractors and ten subcontractors. The Bid opening was scheduled for Monday, Apr1l 27, 1987. On Frlday, Apr11 24, 1987, twelve contractors had expressed interest 1n submltting blds for the llbrary remodel work. HoweVer, on the morning of the bld openlng the Dodge Report (the largest trade industry pub1lcation) publlshed a notlce that the b~d openlng had been postponed untll May 4, 1987. As a result of thlS notlce. many of the contractors who were l.ntendlng to bld - 3 - ., ' . .. , ., . " e e the Job postponed complllng the lr bld packages. The er roneous lnformatlon pub11shed 1n the Dodge Report was a resu1 t of a computer entry error by thelr staff.. Blds were opened and read publ1Cly on Aprll 27, 1987 by the Deputy Clty Clerk. As a result of the erroneous Dodge Report, the Clty recelved only three blds at the bid openlng. Three bids were recelved as follows: H. A. Kaufman Company $ 945,000 $ 960,320 Tyler and CObleigh, Inc. Cavecche Englneerlng and Constructlon Co., Inc. $1,087,600 Clty Englneers's Estlmate: $ 775,000 Staff was lnformed by the bldders that due to the lnformatlon in the Dodge Report thelr blds were h1gher than antlcipated because most subcontractors were not submlttlng blds. Due to the publlsnlng error, staff is recommending that all bids be reJected and the proJect be readvert1sed. It 1S recommended that a new bld openlng date be scheduled for Monday, May 11, 1987, and an award of contract be made on Tuesday, May 12,1987. ThlS wl11 cause a two-week delay in the scheduled constructlon and Ilbrary openlng. Recommendations It 15 recommended that the Clty Council reJect all bids and authorlze staff to readvertise the remodel of the Main Llbrary. prepared by: Stan Scholl, D~rector of General Services Des~ Alvarezr P. E.r City Eng~neer - 4 -