Thi s report reconmends that the C1 ty Counci 1 appropri ate $22,000 from On - Street
Park1ng Funds to cover the cost of additional asphalt and concrete paving removals
and $4,000 from Gas Tax Funds for additlonal traffic signal and street lighting
modifications at the Pica Boulevard and Ocean Avenue intersection.
Background
On July 24, 1979, the City Counc11 awarded a contract for constructing Traffic
Islands and Landscap1ng in Ocean Avenue between Pico Boulevard and Bicknell
Avenue in the amount of $108,615. $22,000 of additional work was subsequently
required to remove an unknown concrete slab and asphalt paving found below the
street surface of Ocean Avenue near Pica. Four thousand dollars of additional
conduit placement was also required to complete the signal modificat1on at
Pica and Ocean. Previously, $81,615 from On-Street Parking Funds and $27,000
from Gas Tax Funds were encumbered.
Therefore, additiona1 appropriations of $22,000 from On-Street Parking Funds and
$4,000 from Gas Tax Funds are requested to finance th1S additional work.
~-o
SEP 2 5 1979
\ '
e
.
To:
Mayor and City Council
-2-
September 14, 1979
This additional work was ordered performed because the project could not stand
ldle until such time as the staff could obtain Council approval. This requested
appropriation is authorizing the funding for work already performed.
Reconmendation
It is recommended that $22,000 from On -Street Parking Funds and $4,000 from
Gas Tax Funds be appropriated to complete the contract for traffic island con-
struction and signal modifications on Ocean Avenue between Pica Boulevard and
Bicknell Avenue.
Prepared by:
Stan Scholl
Doug McAteer
Attachment:
Staff report of 6/26/79
Parking and Landscaping Plan
~
(e
(e
Santa Monica. California
June 26. 1979
10: Mayor and City Council
FROM: City Staff
SUBJECT: Supplement to Item ll-F. Parking and landscaping Plan on Ocean
Avenue between Pico Blvd. and Bicknell Avenue. Award of Contract.
Introduction
This report reconmends that the City Council award a contract for the subject
project to A.M. Construction. Inc.. the lower responsible bidder, in the
amount of $108.615.
Background
Bids for the subject project were opened in the City Council Chambers after
3:00 p.m., Monday, June 25. 1979, and read publicly by the Assistant City
I
Clerk. Plans and Specifications were issued to eight general contractors.
Two bids were received as follows:
Tota 1
A. M. Construction, Inc.
$ 108.615
Sully-Miller Contracting Co. ............. 108,800
City Engineer's Estimate
.
..................
78,100
Estimated Funds necessary:
Contract ................................. $ 108,615
Contingencies ............................
10.000
Construction Engineering ................. 1,385
Total....... $ 120,000
. ,
,
or
(~
Ce
TO: Mayor and City Council
-2-
June 26, 1979
Funding Available:
Off-Street parking fund ....................$
Additional needed ..........................
Total in off-street parking funds
70,000
23,500
$ 93,500
Gas Tax funding for traffic
signal modifications .......................$ 24,320
Contingencies ..............................
2,000
680
Construction Engineering
Total ...
$ 27,000
$ 120,500
Recommendation
-
It is recommended that additional off-street parking revenue funds in the amount
,
of $23,500 and Gas Tax funds in the amount of $27,000 be appropriated, and that
the subject contract be awarded to A.M. Construction, Inc., in the amount of
their low bid of $108,615.
Prepared by:
Stan Scholl
Doug 1':cAteer
Jim Hrenn