SR-505-001-03 (8) EPMW:CP:AA:DP:FJS:EC: F:\DATA\SPFILES\Sp1680 Project 7\CC1680co3.wpd Council Meeting: July 11, 2000 Santa Monica, California TO: Mayor and City Council FROM: City Staff SUBJECT: Recommendation to Authorize the City Manager to Increase the Contingency to Contract 7463 (CCS) with Clarke Contracting, Inc. for Work on Sewer Project 7, and to appropriate $375,000 from the Wastewater Fund Introduction This report recommends that the City Council approve an increase in the contingency to Contract 7463 (CCS) with Clarke Contracting, Inc., for work on Sewer Project 7, Repair of th Earthquake Damaged Sewers in Stewart and 26 Streets between Colorado Avenue and Exposition Boulevard, and in Colorado Avenue between Centinela Avenue and First Court. Staff also recommends that $375,000 be appropriated from the Wastewater Fund to the project. Background At its meeting of March 11, 1999, the City Council awarded a construction contract to Clarke Contracting, Inc. in the amount of $5,394,744, and approved a construction contingency amount of $1,078,949 for work on Sewer Project 7. Contract 7463 (CCS) between the City and Clarke Contracting was executed on April 14, 1999. During the course of sewer construction, a number of changed conditions arose which necessitated the issuance of change orders to Clarke Contracting, Inc. These included changed soils conditions, discovery of unmapped utilities, and the need to substantially increase the depth of the sewer, as well as other unforeseen conditions. Previously 1 approved Change Orders 1 and 2 have depleted most of the contingency reserve, making it necessary to appropriate additional funds for Change Order 3. Discussion Sewer construction under this contract included removal and replacement of 18,885 feet of 12", 15" and 18" sewers with new 18" through 30" sewers along Colorado Avenue and adjacent streets. Work was carried out by traditional open cut methods which required that the contractor make extra efforts to minimize impacts on adjacent businesses as well as pedestrian and vehicle traffic, particularly in the downtown area. Specific unforeseen conditions requiring the appropriation of additional contingency are as follows: 1. Existing average asphalt thickness on Colorado Avenue ranged from 10" to 16", rather than 7" to 8", as had been indicated on earlier As-built drawings. Several unmapped storm drains and connecting laterals were in conflict with the sewer construction and needed to be temporarily removed during construction and later replaced. The contractor was required to install and maintain storm drain bypass piping during outage of the regular storm drains. Additionally, the contractor encountered over-saturated and failing soils at various locations on Colorado Avenue and Stewart Street, as well as abandoned jacking and boring pits on Stewart Street. Additional backfill, compaction and paving were required to correct these problems. The added cost of this work item is $295,000. 2 ndth 2. On Colorado Avenue between 2 and 4 Street, a buried asphalt roadway was discovered approximately 12 feet below the existing road surface. This old roadway interfered with placement of sewer trench shoring and created substantial added problems with excavation, backfilling and compaction. Additionally, related soils problems resulted in damage to an existing 12" water main, requiring that it be removed during construction and later replaced. Because of the increased construction problems, the contractor was required to adjust his schedule to carry out much of the work at night. The added cost of this work item is $195,000. 3. During construction in the downtown area, additional electronic signs, barricades and arrow boards were required to direct and guide pedestrians and motorists through the construction area. Additional flag-persons were assigned to assist with traffic flow at Santa Monica Place parking structures. The added cost of this work item is $20,000. The following shows the status of the original project contingency and the effect of Change Orders 1, 2, and 3: Date Action Amount Remaining Balance Mar 11, 1999 Original Contingency $1,078,949 $1,078,949 Jun 6, 1999 Change Order 1 $ 281,282 $ 797,667 Feb 16, 2000 Change Order 2 $ 627,488 $ 170,179 Pending Change Order 3 $ 510,000 ($ 339,821) 3 Budget/Financial Impact Additional Funds Required Change Order 3 $340,000 Contingency $35,000 Total $375,000 Funds in the amount of $375,000 are available for appropriation from Wastewater Fund 31 to Account Number C31091199.589000. Recommendation Staff recommends that the City Council: 1. Approve an increase in the contingency to construction contract 7463 (CCS) with Clarke Contracting, Inc. in the amount of $375,000. 2. Appropriate an additional $375,000 from Wastewater Fund 31 to account C31091199.589000. 3. Authorize the City Engineer to issue any necessary additional change orders to complete Sewer Project 7 in conformance with City Administrative Instructions on change orders. Prepared by: Craig Perkins, Director, Environmental and Public Works Management Anthony Antich, City Engineer F.J. Schroeder, Disaster Recovery Program Manager Eugenia Chusid, Project Manager 4