R-505ATTACHMENT B
RESOLUTION NUMBER 505 (RAS)
(Redevelopment Series)
A RESOLUTION OF THE REDEVELOPMENT AGENCY OF THE CITY OF SANTA
MONICA ADOPTING THE MITIGATED NEGATIVE DECLARATION FOR THE SANTA
MONICA PLACE REMODEL PROJECT
WHEREAS, Santa Monica Place was approved by the Redevelopment Agency
("Agency") of the City of Santa Monica after a project specific EIR was certified in 1976,
and thereafter the Santa Monica Place project obtained all necessary permits and was
constructed in compliance with them; and
WHEREAS, the Santa Monica Civic Center Specific Plan EIR, certified by the City
Council on June 28, 2005, is a Project EIR forthe proposed Amendment to the Downtown
Redevelopment Plan; and
WHEREAS, environmental review of the proposed Santa Monica Place Remodel
Project is a tiered review under the California Environmental Quality Act; and
WHEREAS, a Draft Initial Study/Mitigated Negative Declaration for the Santa
Monica Place Remodel Project ("Project") was published on July 24, 2007 in compliance
with the California Environmental Quality Act ("CEQA"); and
WHEREAS, the Draft Initial Study/Mitigated Negative Declaration was circulated for
a 30-day public comment period, which ended on August 24, 2007; and
WHEREAS, on August 30, 2007, the Final Mitigated Negative Declaration was
published; and
WHEREAS, the Redevelopment Agency ("Agency') of the City of Santa Monica has
reviewed and considered the proposed mitigated negative declaration together with
comments received during the public review process in its decision-making process;
1
NOW, THEREFORE, THE REDEVELOPMENT AGENCY OF THE CITY OF SANTA
MONICA DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. The Agency has reviewed and considered the information contained in
the Final Mitigated Negative Declaration for the Santa Monica Place Remodel Project
together with comments received during the public review process prior to approving the
Project.
SECTION 2. The Agency finds on the basis of the record before it that there is no
substantial evidence that the Project will have a significant effect on the environment and
that the Final Mitigated Negative Declaration reflects the independent judgement and
analysis of the Agency.
SECTION 3. Consistent with CEQA Guidelines Section 15074(c), the documents
which constitute the record of proceedings upon which this decision is based are located in
the Planning and Community Development Department, 1685 Main Street, Room 212, Santa
Monica, California. The custodian of these documents is the Planning Division Manager.
SECTION 4. Consistent with CEQA Guidelines Section 15074(d), the Agency
adopts the Mitigation Monitoring Program, which is included as Attachment A, to mitigate or
avoid significant environmental effects of the Project, and to ensure compliance with required
conditions of approval during Project implementation.
SECTION 5. The addition of project conditions (including requirements that the
Project applicant notify the Agency of its intent to appeal Project property assessments and
consent to Agency participation in any assessment appeals for the Project property; to
replace sidewalks and pavement on 2"d Street, 4th Street, and Colorado Avenue; install
new and additional lighting and new trees on Colorado Avenue; and remove and replace
the interior stairs and the 2 elevators in parking structure 7 and the elevator in parking
2
eff44
structure 8 are not substantial revisions to the Project and do not require recirculation of
the Mitigated Negative Declaration as provided in CEQA Guidelines Section 15073.5(c)(3).
SECTION 6. The Secretary of the Agency shall certify to the adoption of this
Resolution, and thenceforth and thereafter the same shall be in full force and effect.
APPROVED AS TO FORM:
M SHA OUTRI
G eral C sel
Attachment A: Mitigatiori Monitoring and Reporting Program
3
eff44
Mitigation Monitoring and
Reporting Program
Santa Monica Place Remodel Project IS/MND
Prepared for:
City of Santa Monica
1918 Main Street, Suite 300
Santa Monica, CA 90405
Prepared b~:
Rincon Consultants, Inc.
790 East Santa Clara Street
Ventura, California 93001
July 2007
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Monitoring and Reporting Program
This document is the Mitigation Monitoring and Reporting Program (MMRP) for the Santa Monica Place Remodel Project proposed
in the City of Santa Monica, California. Public Resources Code Section 21081.6(a) requires that a Lead Agency adopt an MMRP
prior to approving a project in order to mitigate or avoid significant impacts that have been identified in an Initial Study/Mitigated
Negative Declaration. The purpose of the MMRP is to ensure that the required mitigation measures identified in the Initial
Study/Mitigated Negative Declaration are implemented as part of the overall project implementation. In addition to ensuring
implementation of mitigation measures, the MMRP provides feedback to agency staff and decision-makers during project
implementation, and identifies the need for enforcement action before irreversible environmental damage occurs.
The following table summarizes the mitigation measures for each issue area identified in the Initial Study/Mitigated Negative
Declaration for the Santa Monica Place Remodel Project. The table identifies each mitigation measure; the action required for the
measure to be implemented; the time at which the monitoring is to occur; the monitoring frequency; and the agency or party
responsible for ensuring that the monitoring is performed. In addition, the table includes columns for compliance verification.
These columns would be filled out by the monitoring agency or party and would document monitoring compliance. Where an
impact was identified to be less than significant, no mitigation measures were required.
This MMRP will be used by City staff or the City's consultant to determine compliance with permit conditions. Violations of these
conditions may cause the City to revoke the operating permit.
City of Santa Monica
2
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Party Initial Date Comments
AESTHETICS
AES-1 Low-Glare Materials. Development shall Implementation of glare- Prior to issuance Once prior to Santa Monica
include screening of mechanical equipment and use of reducing building of permits. issuance of Planning and
low-reflective roofng materials to reduce potential visual components demonstrated permits. Community
and glare impacts. on building plans. Development
Department and
AES-2 Shielded Exterior Lighting. The applicant Architectural
shall design exterior building lighting to ensure that no Review Board
light projects on adjacent sites. Such lighting shall
incorporate "cut-ofP' shields as appropriate to prevent an
increase in lighting at adjacent and nearby uses.
AES3 Shielded Landscape Illumination. Landscape
illumination and exterior sign lighting shall be
accomplished with low-level, unobtrusive fixtures. Such
lighting shall be creatively shielded to direct light pools
awa from off-site viewers.
CONSTRUCTION EFFECTS
CON-1 Fugitive Dust Control Measures. The Implementation of fugitive Prior to issuance Once prior to Santa Monica
following shall be implemented during construction to dust control measures. of permits. issuance of Planning and
minimize fugitive dust and associated particulate permits. Community
emissions: Development
• All material excavated orgraded should be Department
sufficiently watered to prevent excessive Field verifcation during Periodically
amounts of dust. Watering should occur at construction. During during
least three times daily with complete coverage, construction. construction.
preferably at tfie start of the day, in the late
moming and after work is done for the day
• All grading, earth moving or excavation
activities shall cease during periods of high
winds (i.e., greater tfian 20 mph measured as
instantaneous wind gusts) so as to prevent
excessive amounts of dust
• All material transported on and off-site should
be securely covered to prevent excessive
amounts of dust
• Soils stockpiles shall be covered
City of Santa Monica
3
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Party Initial Date Comments
• Onsite vehicle speeds shall be limited to 15
mph
• Install wheel washers where vehicles enter
and exit the construction site onto paved roads
or wash off trucks and any equipment leaving
the site each trip
• Sweep streets at the end of the day using
SCAOMD Rule 1186 certified street sweepers
or roadway washing trucks if visible soil is
carried onto adjacent public paved roads
(recommend water sweepers with reclaimed
water)
• All active portions the construction site shall
be sufficiently watered three times a day to
prevent excessive amounts of dust.
CON-2 Ozone Precursor Control Measures. The Implementation of ozone Prior to issuance Once prior to Santa Monica
following shall be implemented throughout construction precursor control of permits. issuance of Planning and
to reduce emissions of ozone precursors ROC and measures. permits. Community
NOx: Development
• Low VOC coatings shall be used on all Department
remodeled components Periodically
Field verification during During during
• Equipment engines should be maintained in construction. construction. construction.
good condition and in proper tune as per
manufacturer's specifications;
• Schedule construction periods to occur over a
longer time period (i. e. lengthen from 60 days
to 90 days) during the smog season so as to
minimize fhe number of vehicles and
equipment operating simultaneously; and
• Use new technologies to control ozone
precursor emissions as they become readily
available.
CONS NOx Control Measures. Throughout Implementation of NOx Prior to issuance Once prior to Santa Monica
construction, off-road and on-road diesel equipment control measures. of permits. issuance of Planning and
shall use cooled exhaust gas recirculation to reduce permits. Community
emissions of nitrogen oxides. Development
Department
City of Santa Monica
4
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Parly Initial Date Comments
Field verification during
construction.
CON 4 Final Review of Construction Traffic Review and approval of Prior to issuance Once prior to Santa Monica
Management Plan. The final Construction Worksite Construction Traffic of permits. issuance of Planning and
Traffic Control Plan shall be subject to review and Management Plan. permits. Community
approval by the City. The Plan shall include, but not be Development
limited to, the fallowing: Department
• Construction traffic along Santa Monica
Boulevard shall be discouraged during peak
hours (weekday 7-9 a.m. and 4-6 p.m.)
construction traffic may not use Santa Monica
Boulevard. Trucks staging on 2nd Street shall
turn right onto Broadway rather than continuing
north on 2nd Street to Santa Monica
Boulevard. It may be necessary to close the
left turn lane from westbound Broadway to
accommodate this change. To the extent
possible, truck trips should be scheduled
outside of peak traffic hours.
CON-5 Construction Parking Plan. The following Review and approval of Prior to issuance Once prior to Santa Monica
mitigation measures are recommended to address the Construction Traffic of permits. issuance of Planning and
construction period impacts identified above. Management Plan. permits. Community
Development
Department
• Before issuance of a building permit, the applicant
shall submit and obtain approval of a Construction
Parking Plan from the City of Santa Monica Planning
and Community Development Department that contains
the following provisions:
• Construction employee parking shall not be allowed to
reduce the availability of public parking spaces in
Structures 7 and 8 below existing occupancy. If
construction activity does impact the availability of
ublic arkin ,construction workers should shall be
City of Santa Monica
5
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring
to Occur Monitoring
Frequency Responsible
Agency or Compliance Verification
Party Initial Date Comments
required to park in an off-site location with available
parking (such as the Civic Center Parking Structure)
and, if sufficiently far away, be shuttled to the work site.
One of two methods could be used to determine
existing parking occupancy:
1. The results of the occupancy survey already
conducted by Crain and Associates in June 2007 could
be used. This would result in a need to parking
construction workers in an off-site location on weekends
throughout the construction period and on weekdays
during the last few months with high levels of finishing
workers.
2. An additional Parking Demand Analysis could be
performed in advance of or during the mall closure in
order to assess the reduction in parking demand in the
two structures due to closure of retail tenants during
construction. If the results of the Parking Demand
Analysis demonstrate that the estimated or actual
downtown visitor parking occupancy of Structures 7 and
8 during closure is or will be less than that identified in
the June 2007 parking occupancy survey, the
Construction Plan may be modifed to allow additional
construction parking in the structures so long as the
occupied number of public parking spaces is
maintained.
• At present, mall employees park in Structures 7 and 8
on weekdays and in both Structures 7 and 8 and
Structure 5 on weekends (up to 278 mall employees are
presently allowed to park in Structure 5 on weekends). ,
Many of the existing mall retail employees will not be
employed at the mall during the construction period
when the mall shops are closed. During closure of
levels 4, 5 and 6 in Structure 7 during the demolition
hase, remainin mall em to ee arkin should be
City of Santa Monica
6
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Parly Initial Date Comments
relocated from Parking Structures 5, 7, and 8 to the
Civic Center Parking Structure or an alternative
available location outside the downtown area of Santa
Monica on weekends (Saturday and Sunday).
This mitigation measure may only address 250 to 278 of
the roughly 353 space deficit projected in Table 6 for
the demolition phase. It is reasonable to assume,
though, that the remaining 75 to 100 space deficit would
be more than made up by the reduction in Santa
Monica Place patrons that would occur during the
period when the mall is closed.
• Restriping of Structures 7 and 8 should be conducted
by temporarily closing one level at a time in the
structures, on weekdays only, during the lower-demand
period between the demolition phase and the finishing
phase in the last few months when a high level of
workers will be present.
• The demolition phase and its associated closure of
levels 4, 5, and 6 in Structure 7 should not be
conducted at the same time that existing downtown
public parking structures are closed for retrofit or
replacement as part of the Santa Monica downtown
parking program.
GEOLOGY AND SOILS
GEO-1 Seismic Risk Reduction Building Verifcation that structures Prior to issuance Once prior to Santa Monica
Requirements per UBC and CBC Code. Design and are engineered to of permits. issuance of Civil
construction of the Santa Monica Place remodel shall withstand expected ground permits. Engineering
be engineered to withstand the expected ground acceleration and that all and
acceleration that may occur at this site. The calculated structures comply with Architecture.
design base ground motion for the site shall take into provisions of the UBC and
consideration the soil type, potential for liquefaction, CBC.
and the most current and applicable seismic attenuation
methods that are available. All on-site structures shall
comply with applicable provisions of the Uniform
Building Code and the California Building Code.
City of Santa Monica
7
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Party Initial Date Comments
GEO-2 Soil Testing for Expansion Potential. Prior Soil sampling of final sub- Prior to issuance Once prior to Santa Monica
to issuance of a building permit, soil samples of final grade areas. of permits. issuance of Civil
sub-grade areas and excavation sidewalls shall be permits. Engineering
collected and analyzed for their expansion index. For and
areas where the expansion index is found to be greater Architecture
than 20, the appropriate grading and foundation designs
shall be engineered to withstand the existing conditions.
The expansion testing may be omitted if the grading
and foundations are engineered to withstand the
presence of highly expansive soils.
HAZARDS AND HAZARDOUS MATERIALS
HHS-1 Asbestos Containing Material A qualified asbestos Prior to issuance Once prior to Santa Monica
(ACM) Testing. Prior to issuance of a sampling company shall of permits. issuance of Civil
demolition or renovation permit for the Santa conduct an ACM survey. permits. Engineering
Monica Place shopping mall, an ACM survey and
shall be performed by a licensed asbestos Architecture
sampling company. All testing procedures
shall follow California and Federal protocol.
The asbestos survey report shall quantify the
areas of asbestos containing materials
ursuant to California and Federal standards.
HHS-2 ACM Removal Procedure. Prior to any Asbestos trained and Prior to demolition Once prior to Santa Monica
demolition or renovation, onsite structures that contain certified personal or renovation. demolition of Civil
ACM must have the ACMs removed according to proper abatement shall perform renovation. Engineering
abatement procedures recommended by the asbestos asbestos abatement. A and
consultant. All abatement activities shall be in final report detailing the Architecture
compliance with California and Federal OSHA,~and with abatement procedures
the South Coast Air Quality Management District shall be prepared.
requirements. Only asbestos trained and certified
abatement personnel shall be allowed to perform
asbestos abatement. All ACMs removed from onsite
structures shall be hauled to a licensed receiving facility
and disposed of under proper manifest, if needed, by a
transportation company certified to handle asbestos
containing materials. Following completion of the '~,
asbestos abatement, the asbestos consultant shall ''
provide a report documenting the abatement ',
procedures used, the volume of ACM removed, where
the material was moved to, and include transportation
and disposal manifests or dump tickets. Each
City of Santa Monica
8
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Party Initial Date Comments
abatement report shall be prepared for the property
owner or other responsible party, with a copy submitted
to the City of Santa Monica.
HHS-3 Lead-based Paint Testing. Prior to the A licensed lead-based Prior to the Once prior to Santa Monica
issuance of a permit for the renovation or demolition of paint consultant shall be issuance of a the issuance Civil
any structure, a licensed lead-based paint consultant contracted to evaluate the permit for the of a permit for Engineering
shall be contracted to evaluate the structure for lead- structure for lead-based renovation or the and
based paint. If lead-based paint is discovered, it shall paint. If lead-based paint demolition of any renovation or Architecture
be removed according to proper abatement procedures is discovered, it shall be structure. demolition of
recommended by the consultant. All abatement removed according to any structure.
activities shall be in compliance with California and proper abatement
Federal OSHA, and with the South Coast Air Quality procedures recommended
Management District requirements. Only lead-based by the consultant.
paint trained and certified abatement personnel shall be
allowed to perform abatement activities. All lead-based
paint removed from these structures shall be hauled
and disposed of by a transportation company licensed
to transport this type of material. Ih addition, the
material shall be taken to a landfll or receiving facility
licensed to accept the waste. Following completion of
the lead based paint abatement, the lead based paint
consultant shall provide a report documenting the
abatement procedures used, the volume of lead based
paint removed, where the material was moved to, and
include transportation and disposal manifests or dump
tickets. Each abatement report shall be prepared for
the property owner or other responsible party, with a
copy submitted to the City of Santa Monica.
HHS-4 Phase I Environmental Site Assessment. A Phase I environmental Prior to demolition Once prior to Santa Monica
Prior to demolition and development, a Phase I site assessment shall be and development. demolition Civil
environmental site assessment shall be performed to performed by qualified and Engineering
determine the likelihood of contaminants. The Phase I environmental scientists to development. and
ESA shall follow the current ASTM standard (ASTM E determine the likelihood of Architecture
1527-05). All recommendations contained within the contaminants
Phase I Environmental Site Assessment shall be
implemented according to standard regulatory
procedures.
HHS-5 Hazardous Materials Contingency Plan. All Implementation of a During excavation Periodically Santa Monica
demolition and remodeling conducted at the Santa hazardous materials and demolition during Civil
Monica Place mall shall have a contingency plan to be excavation Engineering
City of Santa Monica
9
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Party Initial Date Comments
implemented in the event that contaminants or
structural features that could be associated with
contaminants or hazardous materials are suspected or
discovered. The contingency plan shall identify
appropriate measures to be followed if contaminants
are found or suspected. The appropriate measures
shall identify personnel to be notified, emergency
contacts, and a sampling protocol to be implemented.
The excavation and demolition contractors shall be
made aware of the possibility of encountering unknown -
hazardous materials, and shall be provided with
appropriate contact and notification information. The
contingency plan shall include a provision stating at
what point it is safe to continue with the excavation or
demolition, and identify the person authorized to make
that determination.
NOISE
N 1 Diesel Equipment Mufflers. All diesel Field verification of During Periodically Santa Monica
equipment shall be operated with closed engine doors compliance. construction. during Planning and
and shall be equipped with factory recommended construction. Community
mufflers. Development
De artment
N 2 Electrically-Powered Tools. Electrical power Field verification of During Periodically Santa Monica
shall be used to run air compressors and similar power compliance. construction. during Planning and
tools. construction. Community
Development
Department
N3 Timing Restrictions. The noisiest phases of Field verification of During Periodically Santa Monica
construction shall be restricted to between the hours of compliance. construction. during Planning and
10:00 AM and 3:00 PM, Monday through Friday, in construction. Community
accordance with Section 4.12.110(d) of the Santa Development
Monica Municipal Code. Department
City of Santa
10
Santa Monica Place Remodel Project IS/MND
Mitigation Monitoring and Reporting Program
Mitigation Measure/Condition of Approval Action Required When Monitoring Monitoring Responsible Compliance Verification
to Occur Frequency Agency or
Party Initial Date Comments
N-4 Additional Noise Attenuation Techniques. Field verification of During Periodically Santa Monica
For all noise generating construction activity on the compliance. construction. during Planning and
project site, additional noise attenuation techniques construction. Community
shall be employed to reduce noise levels to City of Development
Santa Monica noise standards. Such techniques may Department
include, but are not limited to, the use of sound blankets
on noise generating equipment and the construction of
temporary sound barriers between construction sites
and nearby sensitive receptors.
N-5 Construction Sign Posting. In accordance Field verification of During Periodically Santa Monica
with Santa Monica Municipal Code Section 4.12.120, compliance. construction. during Planning and
the project applicant shall be required to post a sign construction. Community
informing all workers and subcontractors of the time Development
restrictions for construction activities. The sign shall Department
also include the City telephone numbers where
violations can be reported and complaints associated
with construction noise can be submitted.
City of Santa Monica
11
Adopted and approved this 11th day of September, 2007.
Richard Sloom, Chair
I, hereby certify that the foregoing Resolution No. 505 (RAS) was duly adopted at
a special meeting of the Redevelopment Agency held on the 11th day of September,
2007, by the following vote:
Ayes: Agency members: Genser, McKeown, O'Connor, Shriver
Chair Bloom, Chair Pro Tem Katz
Noes: Agency members: None
Abstain: Agency members: None
Absent: Agency members: Holbrook